N359<br />
Stormwater Improvements - Flood Protection - Clearwater - Smallwood<br />
Circle<br />
Critical Project Milestones<br />
1. Critical Project Milestones<br />
Projected<br />
<strong>District</strong> signage on all construction signs 10/31/2012<br />
2. Contracts<br />
Amended<br />
Actual<br />
Execute Cooperative Agreement 11/07/2011 11/07/2011<br />
2a. Contracts<br />
Add FY2013 funding to Agr. (pending approval) 10/01/2012<br />
3b. Project Activities<br />
Design and Permitting Complete 12/31/2012<br />
3c. Project Activities<br />
Commence Construction 04/01/2013<br />
3d. Project Activities<br />
Complete Construction 04/01/2014<br />
Status As Of February 28, 2012<br />
Current status: The project was approved for FY2012 cooperative funding, and a cooperative funding agreement has been<br />
executed. The City has selected Cumbey & Fair (C&F) as the project consultant and expects to have the Work Order with C&F<br />
approved by City Council by April 5, 2012. The City has applied for FY2013 cooperative funding.<br />