N462<br />

Design & Construction-Pasco County Groves Golf Course Reclaimed <strong>Water</strong><br />

Transmission and Storage Pond Project<br />

Project Type<br />

AORs<br />

<strong>Water</strong> Supply<br />

Cooperative Funding<br />

Strategic Initiatives<br />

Reclaimed <strong>Water</strong><br />

Pasco County<br />

Cooperator(s)<br />

Project Manager Anthony Andrade<br />

Task Manager(s)<br />

Status<br />

Proposed Coop. Funding Application<br />

Recommendation<br />

Fund as a High priority. The project addresses water supply priorities of the Board by implementing reclaimed water supply in the<br />

Central portion of Pasco County. The project is local in its implementation, however it would provide regional benefits as it is near<br />

regional potable water wellfields. The cooperator has confirmed it will request the necessary matching funds in a future capital<br />

improvement program budget. There was sufficient data submitted to evaluate the project, it is within the Board's statutory authority<br />

to fund, and it is not the result of a permit requirement or enforcement action . The County ranked this project 12th on their list of 15<br />

FY2013 CFI requests.<br />

Description<br />

This proposed FY2013 project is for the design and construction of an 8-inch diameter reclaimed water line from the County's<br />

reclaimed water transmission main on US41 to a new isolated pond on the Groves Golf Course property in Land O' Lakes. The<br />

project will provide reclaimed water for irrigation at the Golf Course and some common areas within the community.<br />

Benefits<br />

The project will supply the Groves Golf Course and common areas with 0.25 mgd of reclaimed water to offset 0.18 mgd of existing<br />

irrigation (current source groundwater wells).<br />

Costs<br />

The total cost of the project is estimated to be $200,000, Pasco County has requested $100,000 in FY2013 funding from the<br />

<strong>District</strong> for fifty percent of the funding, however their submitted project schedule shows they will only use a portion ($25,000) of the<br />

share in FY2013. As such, <strong>District</strong> staff reduced the FY2013 <strong>District</strong> grant to only the amount that will be expended in FY2013. The<br />

remaining <strong>District</strong> share ($75,000) is anticipated to be requested in FY2014. The estimated cost, amortized at 8 percent over 30<br />

years is $0.26 per 1000 gallons offset.<br />

Additional Information<br />

Prior<br />

Funding<br />

Cumulative<br />

Transfer or<br />

Lapsed Funding<br />

FY2012<br />

Funding<br />

FY2013<br />

Funding<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

<strong>District</strong> Budgeted - Ad Valorem<br />

Based Revenue<br />

010 General Fund (<strong>District</strong>wide) 0 0 0 66<br />

0<br />

66<br />

013 Hillsborough River Basin 0 0 0 25,000 75,000 100,000<br />

Project Funds Not Budgeted by the<br />

<strong>District</strong><br />

Pasco County 0 0 0 100,000<br />

0 100,000<br />

Total<br />

$200,066<br />

Critical Project Milestones<br />

Projected<br />

Amended<br />

Actual<br />

Commence Design 02/15/2013<br />

Complete Design 08/15/2013<br />

Notice to Proceed Construction 12/01/2013<br />

Complete Construction 09/15/2014<br />

Project Closeout 12/31/2014<br />

Status As Of<br />

48