27.11.2014 Views

2010 Stormwater Management Report (PDF) - US Environmental ...

2010 Stormwater Management Report (PDF) - US Environmental ...

2010 Stormwater Management Report (PDF) - US Environmental ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Total cost for the program was $1,536,000, plus an additional $71,898 for police details.<br />

Under the SBI and CWI, a total of 4,255 manholes were inspected and 6,791 buildings<br />

were dye tested.<br />

These costs for the SBI and CWI programs do not include the cost to correct the illegal<br />

connections found, nor do they include other costs borne by the Commission for<br />

activities, such as performing additional dye tests, cleaning pipes and manholes, program<br />

management, construction oversight and other support services.<br />

In October 2008, the Commission executed a contract for continuation of its Citywide<br />

Illegal Connection Investigation Program. The contract duration for the Phase 2 program<br />

is four years. Since Phase 2 started, a total of 1,766 manhole inspections have been<br />

performed and 1,916 buildings have been dye tested under Phase 2. This is an increase<br />

from 1,120 manholes inspected and 565 buildings dye tested under the program in 2009.<br />

Total estimated cost for Phase 2 is $1,360,000. As of the end of <strong>2010</strong>, $965,425 had been<br />

expended for the contract services under Phase 2, and $68,812 had been spent on police<br />

details.<br />

The cost borne by the Commission to correct 18 illegal connections in <strong>2010</strong> was<br />

approximately $189,936, not including the cost for police details, permits, inspection<br />

fees, or for permanent paving over the excavations. This cost also does not include costs<br />

borne by the owners who were required to correct illegal connections on their own<br />

properties.<br />

2.3 INVESTIGATION METHODOLOGY<br />

The Commission’s method for illegal connection investigations under the SBI, Phase 1<br />

and Phase 2 is a “top-down” approach, meaning that the investigations start at the upper<br />

reaches of drainage areas and proceed downstream as illegal connections and other<br />

problems are identified and resolved. Visual inspections of storm drain manholes are<br />

performed after 24 to 48 hours of dry weather. If flow is observed in a manhole, the flow<br />

is tested in the field for ammonia and surfactants using a field test kit. If no flow is<br />

observed, manholes at key junctions of the sub-drainage area are sandbagged for 24 to 48<br />

hours to capture possible intermittent flow from upstream storm drains. Any flow that is<br />

captured after 24 to 48 hours of sandbagging is inspected and field tested for evidence of<br />

contamination. If evidence of contamination exists, upstream buildings are dye tested to<br />

determine the locations of the illegal connection. Once the illegal connection is located,<br />

it is added to a Commission construction contract for correction. After the illegal<br />

connection is corrected, a post correction check of the drain is performed using similar<br />

investigative procedures. This ensures that no sources of contamination are missed.<br />

2 - 2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!