7.0 ENFORCEMENT<br />

The Commission’s approach to enforcement is generally proactive in that it focuses<br />

primarily on public and contractor education, and requiring proper site planning by<br />

developers. Enforcement, including fines, is supported by the Commission Sewer Use<br />

Regulations and the Site Plan Requirements.<br />

The Commission’s method of enforcement varies, depending on the type and magnitude<br />

of the violation. In most cases, the Commission prefers to work with violators or<br />

responsible parties to ensure that the problem is quickly and effectively remedied. If the<br />

owner fails to take action and remedy the problem, a letter of violation is issued and a<br />

fine may be assessed.<br />

In <strong>2010</strong>, Field Engineering responded to 63 reports of a potential spill, leak, or report of<br />

illicit dumping. Table 3 – 3 in section 3.2. lists the incidences to which the Commission<br />

responded in <strong>2010</strong>. Enforcement notices were issued by staff in 9 of those instances.<br />

Fines were assessed in 3 instances.<br />

7 - 1