29<br />

5.3.4 Water installation<br />

Master Slave 1...3<br />

Y6 **<br />

Y3 Y4 Y5<br />

Y3 Y4 Y5<br />

M20x1.5<br />

ø19 mm hose connector<br />

or G 1/2" inside thread<br />

Notes on water installation<br />

– Use hoses to connect the supply flushing line and the tub drain to an open drain funnel (make<br />

sure to install the hoses correctly).<br />

– The working pressure flushing valve Y6 (**) is mounted directly to the step valve block of the<br />

Master unit (stand-alone system) or the last Slave unit (Compound systems). The drain hose<br />

of the flushing valve is to be connected to an open drain funnel (make sure to install the hose<br />

correctly).<br />

– Use only the optional high-pressure hoses to establish the high-pressure piping between the<br />

high-pressure connection of the pump station and the step valve block (or between step valve<br />

blocks of the Slave units, respectively). Other hoses may get damaged in operation and cause<br />

system breakdown.