04.04.2015 Views

Part I

Part I

Part I

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Draft Black Sea Regional Transmission Project ESIA<br />

2.1.3.2 Transmission Lines<br />

In forested areas, the right-of-way will require vegetation control measures to maintain<br />

clearance for transmission lines and to maintain access to the towers. Vegetation control<br />

will be conducted mechanically, with cutting<br />

activities occurring every 6 to 8 years.<br />

Herbicides will not be used for vegetation<br />

control. An example of a cleared corridor in<br />

forested terrain is shown in Figure 2-7.<br />

Access to towers locations will be achieved by<br />

driving to existing road crossings and entering<br />

the right-of-way by driving over the ground or<br />

by driving along dirt access roads (where they<br />

exist along the existing sections of the line).<br />

Neither permanent nor temporary<br />

paved/gravel access roads will be established<br />

and maintained in the right-of-way.<br />

In some locations (including that portion of the<br />

route traversing the Borjomi-Karagauli<br />

National Park), construction and maintenance<br />

access is will be by helicopter. Vegetation<br />

Figure 2-7. Example of vegetation clearing<br />

for corridor maintenance in forested terrain<br />

control at the tower locations will be conducted manually by workers every six to eight years.<br />

Because of the placement of the towers on high points, vegetation control in these areas of<br />

the right-of-way may not always be required in order to maintain adequate clearance<br />

between vegetation and lines.<br />

2.2 Alternative 2 – Modified Route Near Ktsia-Tabatskuri Managed Reserve and<br />

through Borjomi-Kharagauli National Park<br />

Alternative 2 uses most of the original project route described in Alternative 1. However,<br />

Alternative 2 involves a realignment of the route near Ktsia-Tabatskuri Managed Reserve in<br />

order to reduce potential impacts to that protected area. It also involves crossing Borjomi-<br />

Kharagauli National Park at its narrowest point and at areas quite distant from recreational<br />

traffic. This alternative can also include some technological alternatives to minimize landclearing<br />

in the National Park, which would further mitigate potential impacts. This alternative<br />

is shown in Figure 2-8.<br />

The modified route is 294 kilometers long, about 11 kilometers longer than Alternative 1, and<br />

would involve constructing 350 or more new towers in addition to using 514 of the existing<br />

towers. It also would involve abandoning 40 existing towers. The crossing of Borjomi-<br />

Kharagauli would be 4.7 kilometers long, compared to 11.5 kilometers in Alternative 1. The<br />

crossing of Ktsia-Tabatskuri would be 10 kilometers long, compared to 12.1 kilometers in<br />

Alternative 1.<br />

This alternative was developed based on consultations with the Agency for Protected Areas<br />

in the Ministry of Environment Protection and Natural Resources In a series of meetings, the<br />

Agency expressed concern over visual impacts to recreational bird-watching and impacts to<br />

bird species near Tabatskuri Lake, an alpine lake. As a result, this alternative creates a new<br />

alignment that roughly parallels the recently installed BTC pipeline and avoids the areas of<br />

concern to the Agency for Protected Areas. In addition, the Agency expressed concern over<br />

potential impacts in Borjomi-Kharagauli National Park, so the route was modified so it would<br />

cross the park at its narrowest point.<br />

20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!