04.04.2015 Views

Part I

Part I

Part I

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Draft Black Sea Regional Transmission Project ESIA<br />

completed a study for the Ministry that evaluated the concept of developing an extremely<br />

high-voltage interconnected system in Caucasus nations. The intent would be to allow easy<br />

and efficient cross-border exchanges and make better use of regional energy resources.<br />

The study considered Georgia, Armenia, Azerbaijan, Iran, and Turkey. The study<br />

recommended going forward with the two projects studied in detail, which were to develop<br />

lines to connect Armenia and Georgia, and to connect Turkey and Georgia. The study<br />

concluded that Georgia (and Armenia) would profit from and share in development<br />

momentum that would be gained by Turkey, Iran, Azerbaijan, and Russia.<br />

The Ministry of Energy also commissioned a study (Ministry of Energy of Georgia, undated)<br />

to determine whether there is adequate demand in Turkey for electricity exported from<br />

Georgia and Azerbaijan and whether there is sufficient existing and feasible electricity<br />

generation projects in Azerbaijan and Georgia to supply the Turkish markets using a newly<br />

constructed transmission line. The study determined that this was feasible, given a<br />

competitive price and additional investment in hydropower generation facilities in Georgia.<br />

The study also noted that the hydropower investment would likely depend on there being a<br />

firm commitment to the transmission line, whereas financing for the transmission line would<br />

depend on commitments to generation projects.<br />

Finally, the Ministry of Energy sponsored a feasibility study funded by the United States<br />

Trade and Development Agency to determine the least-cost technical options to make power<br />

transmission more reliable in Georgia (Kuljian, 2008). Specifically, the study examined the<br />

construction of a new 500kV line that would further integrate the west and east Georgian<br />

Power System and operate in parallel with the existing Zestaphoni – Ksani – Gardabani<br />

500kV transmission line. The study also examined the feasibility of having this new line,<br />

which would be a completion of the old Soviet-era planned line, also have a new high<br />

voltage interconnection to Turkey by way of a new substation at Akhaltsikhe. Although there<br />

has been some deterioration and scavenging, much of the constructed route remains<br />

suitable for use after some rehabilitation.<br />

Subsequently, the Ministry of Energy made a decision to go forward with completion of the<br />

line and approached lenders for financing. The Project Execution Agency for the project is<br />

the Georgia State Electrosystem (GSE), which will be responsible for designing and<br />

constructing the line together with the Technical Consultant hired through international<br />

tender specifically for the Black Sea Transmission Project. As the project progresses, GSE<br />

may pass along responsibility as the execution agency to EnergoTrans, the daughter<br />

company (100 percent ownership), which is the legal entity that owns portions of the line that<br />

have already been acquired and will own the entire line once the right-of-way is fully<br />

acquired.<br />

1.3 Scope of the ESIA<br />

This Environmental and Social Impact Assessment (ESIA) evaluates the following project<br />

components, as shown on Figure 1-1:<br />

<br />

<br />

<br />

<br />

Rehabilitation and reconstruction of foundations and/or towers that have<br />

deteriorated or been damaged along the 260-kilometer route from Gardabani to<br />

Zestaphoni.<br />

Construction of foundations and towers for sections of the line that were not built<br />

on the Gardabani to Zestaphoni route and on the 30-kilometer route from<br />

Akhaltsikhe to the Turkish border.<br />

Conductoring (that is, placing lines to conduct electricity) the entire line.<br />

Slight expansions of existing 500kV substations near Gardabani and Zestaphoni.<br />

2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!