Part I
Part I
Part I
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Draft Black Sea Regional Transmission Project ESIA<br />
completed a study for the Ministry that evaluated the concept of developing an extremely<br />
high-voltage interconnected system in Caucasus nations. The intent would be to allow easy<br />
and efficient cross-border exchanges and make better use of regional energy resources.<br />
The study considered Georgia, Armenia, Azerbaijan, Iran, and Turkey. The study<br />
recommended going forward with the two projects studied in detail, which were to develop<br />
lines to connect Armenia and Georgia, and to connect Turkey and Georgia. The study<br />
concluded that Georgia (and Armenia) would profit from and share in development<br />
momentum that would be gained by Turkey, Iran, Azerbaijan, and Russia.<br />
The Ministry of Energy also commissioned a study (Ministry of Energy of Georgia, undated)<br />
to determine whether there is adequate demand in Turkey for electricity exported from<br />
Georgia and Azerbaijan and whether there is sufficient existing and feasible electricity<br />
generation projects in Azerbaijan and Georgia to supply the Turkish markets using a newly<br />
constructed transmission line. The study determined that this was feasible, given a<br />
competitive price and additional investment in hydropower generation facilities in Georgia.<br />
The study also noted that the hydropower investment would likely depend on there being a<br />
firm commitment to the transmission line, whereas financing for the transmission line would<br />
depend on commitments to generation projects.<br />
Finally, the Ministry of Energy sponsored a feasibility study funded by the United States<br />
Trade and Development Agency to determine the least-cost technical options to make power<br />
transmission more reliable in Georgia (Kuljian, 2008). Specifically, the study examined the<br />
construction of a new 500kV line that would further integrate the west and east Georgian<br />
Power System and operate in parallel with the existing Zestaphoni – Ksani – Gardabani<br />
500kV transmission line. The study also examined the feasibility of having this new line,<br />
which would be a completion of the old Soviet-era planned line, also have a new high<br />
voltage interconnection to Turkey by way of a new substation at Akhaltsikhe. Although there<br />
has been some deterioration and scavenging, much of the constructed route remains<br />
suitable for use after some rehabilitation.<br />
Subsequently, the Ministry of Energy made a decision to go forward with completion of the<br />
line and approached lenders for financing. The Project Execution Agency for the project is<br />
the Georgia State Electrosystem (GSE), which will be responsible for designing and<br />
constructing the line together with the Technical Consultant hired through international<br />
tender specifically for the Black Sea Transmission Project. As the project progresses, GSE<br />
may pass along responsibility as the execution agency to EnergoTrans, the daughter<br />
company (100 percent ownership), which is the legal entity that owns portions of the line that<br />
have already been acquired and will own the entire line once the right-of-way is fully<br />
acquired.<br />
1.3 Scope of the ESIA<br />
This Environmental and Social Impact Assessment (ESIA) evaluates the following project<br />
components, as shown on Figure 1-1:<br />
<br />
<br />
<br />
<br />
Rehabilitation and reconstruction of foundations and/or towers that have<br />
deteriorated or been damaged along the 260-kilometer route from Gardabani to<br />
Zestaphoni.<br />
Construction of foundations and towers for sections of the line that were not built<br />
on the Gardabani to Zestaphoni route and on the 30-kilometer route from<br />
Akhaltsikhe to the Turkish border.<br />
Conductoring (that is, placing lines to conduct electricity) the entire line.<br />
Slight expansions of existing 500kV substations near Gardabani and Zestaphoni.<br />
2