CAPITAL CONSTRUCTION QUARTERLY STATUS REPORT<br />

As of June 30, 2007<br />

<strong>College</strong>: Peru <strong>State</strong> <strong>College</strong> Meeting Date: <strong>September</strong> <strong>13</strong>-<strong>14</strong>, 2007<br />

Project Information Project Title: Emergency Power Generation<br />

Program Number:<br />

Professional Consultant:<br />

Leo A Daly<br />

General Contractor:<br />

To Be Determined from Bids<br />

Net Square Footage: NA Gross Square Footage: NA<br />

Bid Opening Date Generator 2/<strong>13</strong>/07, Installation 3/<strong>13</strong>/07<br />

Notice to Proceed Date<br />

Estimated Completion Date 9/1/2007<br />

Final Acceptance Date<br />

Project Dates<br />

Professional Consultants:<br />

Needs <strong>State</strong>ment<br />

Program <strong>State</strong>ment<br />

Professional Services Contract 9/15/2006<br />

Bonds Sold 8/15/2006<br />

Preliminary Plans<br />

Design Development<br />

Construction Contract<br />

Substantial Completion 9/1/2007<br />

Final Completion<br />

Report Information Status Initial Report:<br />

Interim Report: X<br />

Final Report:<br />

Financial Information<br />

<strong>State</strong> Buildings Proposed Budget Expended to Date Balance<br />

<strong>State</strong> Funds--LB No:605 $802,500.00 $69,572.57 $732,927.43<br />

Transferred to AWAC -$<strong>14</strong>9,500.00 -$<strong>14</strong>9,500.00<br />

Total Available $653,000.00 $69,572.57 $583,427.43<br />

Revenue Bond Buildings Bonds Sold $<br />

Costs of Issuance/Reserves $<br />

Balances of Proceeds $<br />

Revenue Sources for 1. Bond Proceeds $<br />

Construction 2. Interest Earnings $<br />

3. Other $<br />

Total Available $<br />

Expenditure Information Proposed Budget Expended to Date Balance<br />

Program Planning $0.00<br />

Professional Fees $70,000.00 $67,710.43 $2,289.57<br />

Life Cycle Cost Analysis $0.00<br />

Construction<br />

1. General, Mech., Elec. $582,000.00 $582,000.00<br />

2. Fixed Equipment $0.00<br />

3. Site work/Utilities $0.00<br />

Furnishings/Moveable Equip. $0.00<br />

Contingency $0.00<br />

Artwork $0.00<br />

Other Items<br />

1.Administrative Fees $1,000.00 $1,862.<strong>14</strong> -$862.<strong>14</strong><br />

2.Relocaton $0.00<br />

3.Testing and Surveys $0.00<br />

4.Asbestos Abatement $0.00<br />

5.Legal fees and Insurance $0.00<br />

Change Orders<br />

TOTALS $653,000.00 $69,572.57 $583,427.43