oth national and international interest.<br />
• Holistic approach: The project must take<br />
due regard of lifecycle costs.<br />
• Duration of the contract: Approximately 25<br />
years should be permitted, with no<br />
reconstruction in the near future.<br />
• Final financing: This should be through<br />
cofinancing. Alternatively, user fees could<br />
finance all or part of the investment.<br />
Pipeline Of Potential PPP Projects<br />
The working group identified four projects it<br />
believed to fulfill all key criteria (see table 2).<br />
The working group subsequently identified<br />
projects that could be suitable for PPP, but that<br />
do not currently fulfill all essential criteria<br />
(see table 3).<br />
Similarly, the working group identified railroad<br />
projects that should be continually evaluated as to<br />
their suitability for PPP financing. These are:<br />
Railroad East (Ostlänken); Railroad Norrbotten<br />
(Norrbotniabanan); a railroad between Mölnlycke<br />
and Rävlanda/Bollebygd; a railroad between<br />
Malmö, Staffanstorp, and Dalby<br />
(Simrishamnsbanan); and combination terminals<br />
and connections to harbors. ■<br />
STANDARD & POOR’S EUROPEAN INFRASTRUCTURE FINANCE YEARBOOK<br />
PROJECT FINANCE/PUBLIC-PRIVATE PARTNERSHIPS<br />
Table 2 - Prospective Projects That Meet All Criteria For PPP Financing<br />
Length (kilometers) <strong>In</strong>vestment (mil. SEK) NNK* (x)<br />
Riksväg 50 road between Mjölby and Motala 28 1,330 1.4<br />
E22 motorway between Hurva and Kristianstad 41 (57) 1,100 (1,360) 0.7<br />
E4 Sundsvall South motorway 22 2,500 0.9<br />
Länsväg 259 Södertörn road 9 1,300 0.7<br />
*NNK (nettonuvärdeskvot) measures profitability and needs to be at least 0.5x. SEK--Swedish krona.<br />
Table 3 - Prospective Projects That Meet Some Criteria For PPP Financing<br />
Length (kilometers) <strong>In</strong>vestment (mil. SEK) NNK* (x)<br />
E22 motorway between Kristianstad and Karlshamn 53 1,430 0.5<br />
E22 motorway between Karlshamn and Jämjö 69 (74) 1,840 0.0<br />
E22 Söderköping motorway 17 700 0.7-1.9<br />
E6/45 new connection to river 1.5 2,500 2.2<br />
E20 motorway between Alingsås and Vårgårda 25 1,550 0.5<br />
E4 motorway between Hjulsta and Häggvik 7 4,500 0.2<br />
E4 motorway between Södertälje and Hallunda 15 3,300 N.A.<br />
E12 Umeå motorway (Umepaketet) 28 1,100 0.0-2.1<br />
*NNK (nettonuvärdeskvot) measures profitability and needs to be at least 0.5x. SEK--Swedish krona. N.A.--Not available.<br />