Water Supply Plan - City of Miami
Water Supply Plan - City of Miami
Water Supply Plan - City of Miami
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
ID Project Reuse Flow(a)<br />
(MGD)<br />
Estimated Capital<br />
Cost(b) $(Million)<br />
1 HLD at SDWWTP 505.0<br />
2 New Upper Floridan Aquifer R.O. WTP (WTP Capacity)<br />
3 Phase 1 (10 MGD) 93.0<br />
7 Phase 2 (5 MGD) 25.0<br />
11 Phase 3 (2.5 MGD) 9.7<br />
15 Floridan Aquifer Blending at Alexander-Orr WTP (7.2 MGD) 6.4<br />
17 Floridan Aquifer Blending Wellfield at Hialeah/Preston (4.7 MGD) 10.3<br />
21 North District (Interama) WWTP Reuse Projects (2.0 MGD) 7 26.8<br />
25 Central District (Virginia Key) WWTP Reuse Projects (1.0 MGD) 1 15.3<br />
29 <strong>Water</strong> Reclamation <strong>Plan</strong>t (WRP) Projects<br />
30 Phase 1 (SDWRP GW Recharge, 18 MGD) 30 357.5<br />
35 Phase 2 (WDWRP Canal Recharge, 20 MGD) 28 482<br />
39 Phase 3 (WDWRP Canal Recharge, 15 MGD) 21 317<br />
43 Miscellaneous Programs/Projects/Studies<br />
44 <strong>Water</strong> Conservation/UFW Reduction Program (Up to 19.62 MGD) 25.2<br />
45 Coastal Wetland Rehydration Demo Pilot Project (Conceptual <strong>Plan</strong>) 19.2<br />
46 Aquifer Recharge Pilot Study (20,000 GPD) 0.02 1.0<br />
47 Other AWS Studies/Evaluations 2.0<br />
48 SMH WTP Program 185.2<br />
52 TOTALS 87.27 2,080.6<br />
(a) Exclusive <strong>of</strong> Coastal Wetlands Rehydration Project (78 mgd)<br />
(b) December, 2006 (ENR CCI = 7888)<br />
<strong>Miami</strong>-Dade Reuse and Alternative <strong>Water</strong> <strong>Supply</strong> Conceptual Programs (10/31/2007)<br />
2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030<br />
Figure 5-2<br />
11/1/07<br />
Reuse Program ScheduleRev.mpp