ID Task Name Start Finish<br />

1 New Upper Floridan Aquifer R.O. WTP (WTP Capacity) 5/2/07 12/28/27<br />

2 Phase 1 (10 MGD) 5/2/07 12/25/11<br />

3 <strong>Plan</strong>ning/Design 5/2/07 12/12/08<br />

4 Permitting/Procurement 12/13/08 12/7/09<br />

5 Construction/Start-up 12/8/09 12/25/11<br />

6 Phase 2 (5 MGD) 1/1/15 12/27/17<br />

7 <strong>Plan</strong>ning/Design 1/1/15 10/27/15<br />

8 Permitting/Procurement 10/28/15 7/25/16<br />

9 Construction/Start-up 7/26/16 12/27/17<br />

10 Phase 3 (2.5 MGD) 1/1/25 12/28/27<br />

11 <strong>Plan</strong>ning/Design 1/1/25 10/27/25<br />

12 Permitting/Procurement 10/28/25 7/24/26<br />

13 Construction/Start-up 7/27/26 12/28/27<br />

14 Floridan Aquifer Blending at Alexander-Orr WTP (7.2 MGD) 1/1/07 6/29/07<br />

15 Start-up 1/1/07 6/29/07<br />

16 Floridan Aquifer Blending Wellfield at Hialeah/Preston (4.2 MGD) 8/11/06 12/24/09<br />

17 <strong>Plan</strong>ning/Design 8/11/06 2/3/08<br />

18 Permitting/Procurement 2/4/08 12/29/08<br />

19 Construction/Start-up 12/30/08 12/24/09<br />

20 North District (Interama) WWTP Reuse Project (7.0 MGD) 10/2/07 10/15/11<br />

21 <strong>Plan</strong>ning/Design 10/2/07 1/23/09<br />

22 Permitting/Procurement 1/24/09 1/23/10<br />

23 Construction/Start-up 1/24/10 10/15/11<br />

24 Central District (Virginia Key) WWTP Reuse Project (1.0 MGD) 10/2/07 10/15/11<br />

25 <strong>Plan</strong>ning/Design 10/2/07 1/23/09<br />

26 Permitting/Procurement 1/24/09 1/23/10<br />

27 Construction/Start-up 1/24/10 10/15/11<br />

28 <strong>Water</strong> Reclamation <strong>Plan</strong>t (WRP) Projects 1/1/07 12/31/25<br />

29 Phase 1 (SDWRP GW Recharge, 18 MGD) 1/1/07 12/1/13<br />

30 Study 1/1/07 12/26/07<br />

31 <strong>Plan</strong>ning/Design 12/27/07 8/19/09<br />

32 Permitting/Procurement 8/20/09 8/19/10<br />

33 Construction/Start-up 8/20/10 12/1/13<br />

34 Phase 2 (WDWRP Canal Recharge, 20 MGD) 1/2/15 8/7/20<br />

35 <strong>Plan</strong>ning/Design 1/2/15 8/23/16<br />

36 Permitting/Procurement 8/24/16 8/23/17<br />

37 Construction/Start-up 8/24/17 8/7/20<br />

38 Phase 3 (WDWRP Canal Recharge, 15 MGD) 1/2/21 12/31/25<br />

39 <strong>Plan</strong>ning/Design 1/2/21 7/15/22<br />

40 Permitting/Procurement 7/16/22 7/15/23<br />

41 Construction/Start-up 7/16/23 12/31/25<br />

42 Miscellaneous Programs/Projects/Studies 7/3/06 7/1/26<br />

43 <strong>Water</strong> Conservation (Up to 19.62 MGD) 7/3/06 7/1/26<br />

44 CW Rehydration Demo <strong>Plan</strong>t (0.25 MGD) (Conceptual <strong>Plan</strong>) 8/8/06 11/10/07<br />

45 Aquifer Recharge Pilot Study (20,000 GPD) 9/1/06 8/3/09<br />

46 Other AWS Studies/Evaluations 12/5/06 12/3/08<br />

47 SMH WTP Program 1/29/04 7/4/11<br />

48 <strong>Plan</strong>ning/Design 1/29/04 6/30/07<br />

49 Permitting/Procurement 7/1/07 6/29/08<br />

50 Construction/Start-up 6/30/08 7/4/11<br />

<strong>Miami</strong>-Dade Reuse and Alternative <strong>Water</strong> <strong>Supply</strong> (AWS) Conceptual Programs (10/31/2007)<br />

20-Year <strong>Water</strong> Use Permit<br />

LEGEND: STUDY PLANNING/DESIGN PERMITTING/PROCUREMENT CONSTRUCTION/START-UP<br />

A<br />

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028<br />

FIGURE 2<br />

11/15/07<br />

<strong>Water</strong><strong>Supply</strong>Projects.mpp