04.12.2012 Views

Water Supply Plan - City of Miami

Water Supply Plan - City of Miami

Water Supply Plan - City of Miami

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Water</strong> Facilities Master <strong>Plan</strong><br />

<strong>Water</strong> <strong>Supply</strong> Facilities Work <strong>Plan</strong><br />

A 5-8<br />

KM2740.Sec5a .doc<br />

11/26/2007<br />

blending AADD capacity to the County’s water supply. This project uses the brackish<br />

Floridan Aquifer water to blend with the fresh Biscayne Aquifer raw water.<br />

MDWASD also anticipates using these wells for occasional storage <strong>of</strong> fresh Biscayne<br />

Aquifer water in the Floridan Aquifer during the wet season for extraction and use in<br />

the dry season. To do so, MDWASD designed a ultra-violet (UV) light disinfection<br />

system for each ASR site. Project construction costs totaled $6.4 million (for the UV<br />

system).<br />

5.2.3 Floridan Aquifer Blending Wellfield at Hialeah-Preston<br />

<strong>Water</strong> Treatment <strong>Plan</strong>ts (4.7 MGD)<br />

Start 2006<br />

Finish 2010<br />

MDWASD is planning on constructing two Floridan Aquifer blending wells to supply<br />

raw water to the Hialeah-Preston WTP complex. This project will further increase<br />

AADD capacity by 4.7 MGD by blending the Floridan Aquifer water with the raw<br />

water supply at an estimated cost <strong>of</strong> $10.3 million by 2010. This project is currently<br />

under design by MDWASD.<br />

5.2.4 North District Wastewater Treatment <strong>Plan</strong>t (NDWWTP)<br />

(7.0 MGD)<br />

Start 2007<br />

Finish 2011<br />

This project is a 7 MGD reclaimed water (e.g. purple pipe) irrigation project at the<br />

NDWWTP with an estimated cost <strong>of</strong> $26.8 million and its completion is scheduled for<br />

2011. Part <strong>of</strong> the reclaimed water will be pumped to the <strong>City</strong> <strong>of</strong> North <strong>Miami</strong> Beach.<br />

Approximately 2 MGD will be used to replace a current potable water irrigation in the<br />

MDWASD service area as a potable water credit. MDWASD has prepared a NTPC<br />

for selecting a Consultant to design the project, and will take the requests to advertise<br />

to the December 2007 Board <strong>of</strong> County Commissioners.<br />

5.2.5 Central District Wastewater Treatment <strong>Plan</strong>t (CDWWTP)<br />

(1.0 MGD)<br />

Start 2007<br />

Finish 2011<br />

This project is a 1 MGD reclaimed water (e.g. purple pipe) irrigation project at the<br />

CDWWTP with an estimated cost <strong>of</strong> $15.3 million and its completion is scheduled for<br />

2011. The project will replace potable water irrigation at Crandon Park and certain<br />

areas <strong>of</strong> Key Biscayne as a potable water credit. MDWASD has prepared a NTPC for<br />

selecting a Consultant to design the project, and will take the requests to advertise to<br />

the December 2007 Board <strong>of</strong> County Commissioners.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!