Fort Nelson NRRM NOISE VIBRATION AND SECTION 15200<br />
Airport Terminal Building SEISMIC CONTROL Page: 2<br />
Washroom Renovations<br />
7. Brace fuel gas and oil piping, medical gas piping and compressed air piping 25mm [1"] and<br />
larger, all piping 32mm [1-1/4"] and larger located in boiler rooms, mechanical equipment<br />
rooms and refrigeration machinery rooms and all pipes 65mm [2 ½"] diameter and larger in all<br />
locations as follows:<br />
- Provide pipe transverse bracing at 12.2m [40'] maximum centres unless otherwise noted.<br />
On gas piping transverse bracing shall be at 6.1m [20'] maximum centres.<br />
- Provide pipe longitudinal bracing at 24.4m [80'] maximum centres unless otherwise<br />
noted. On gas piping longitudinal bracing shall be at 12.2m [40'] maximum centres.<br />
- Transverse bracing for one pipe section may also act as longitudinal bracing for a section<br />
connected perpendicular to it, if the bracing is installed within two feet of the elbow or<br />
tee of similar size.<br />
- Do not use branch lines to brace main lines<br />
- Trapeze pipe hangers may be used. Provide flexibility in joints where pipes pass<br />
through building seismic or expansion joints, or where rigidly supported pipes connect<br />
to equipment with vibration isolators.<br />
- Rigid piping shall not be braced to dissimilar parts of a building or building systems.<br />
Examples: Wall and roof; solid concrete wall and a metal deck with lightweight concrete<br />
fill.<br />
- Provide pipe sleeves through walls and floors large enough to accommodate differential<br />
movements.<br />
8. Vertical Piping shall be:<br />
- Secured at sufficiently close intervals to keep pipe in alignment and carry weight of pipe<br />
and contents. Stacks shall be supported at their bases and if over two stories in height at<br />
each floor by approved metal floor clamps.<br />
- Support I.P.S. screwed pipe at not less than every other storey height.<br />
- Support copper tubing 38mm [1½"] and larger diameter at each storey and smaller<br />
tubing at not more than 1.8m [6'] intervals.<br />
- For other approved pipe materials support in accordance with their approved installation<br />
standards.<br />
- Supported at a point or points above riser centre of gravity.<br />
- Laterally guided at top and bottom of riser and at points not to exceed 9.1m [30‘] on<br />
centre.<br />
February 2012 JM BEAN & CO. LTD 1130.10