<strong>International</strong> building costs, in <strong>2016</strong><br />

EUR<br />

USD<br />

(exchange<br />

rate: 0.92)<br />

Retail<br />

Large shopping centre including mall 2,600 2,830<br />

Neighbourhood incl super<strong>market</strong> 2,350 2,550<br />

Prestige car showroom 2,900 3,150<br />

Composite trade rates<br />

Excavate basement (m 3 ) (1800m 3 job) 12 13<br />

Excavate footings (m) 22 24<br />

Concrete in slab (m 3 ) (1500m 3 job) 155 168<br />

Reinforcement in beams (tonne) 1,050 1,141<br />

Formwork to soffit of slab (m 2 ) 40 43<br />

Blockwork in wall (m 2 ) (10,000 block job) 28 30<br />

Structural steel beams (tonne) 2,025 2,201<br />

Pre-cast concrete wall (m 2 ) 95 103<br />

Curtain wall glazing incl support system (m 2 ) (1000m 2 job) 550 598<br />

Plasterboard 13mm thick to stud wall (m 2 ) (3000m 2 job) 60 65<br />

Single solid core door incl frame and hardware (no) (50 door job) 800 870<br />

Painting to walls primer + 2 coats (m 2 ) 8 9<br />

Ceramic tiling (m 2 ) (1000m 2 job) 70 76<br />

Vinyl flooring to wet areas (m 2 ) (500m 2 job) 38 41<br />

Carpet medium tufted (m 2 ) (4500m 2 job) 34 37<br />

Lighting installation (m 2 ) (5000m 2 + job) 53 58<br />

Copper pipe 15mm to wall (m) (1000+ metre job) 33 36<br />

Fire sprinklers (per m 2 ) (5000m 2 job) 86 93<br />

Air conditioning incl main plant (m 2 ) (5000m 2 + job) 155 168<br />

Labour costs<br />

Group 1 Tradesman e.g. plumber, electrician 32 35<br />

Group 2 Tradesman e.g. carpenter, bricklayer 32 35<br />

Group 3 Tradesman e.g. carpet layer, tiler, plasterer 32 35<br />

General labourer 25 27<br />

Site foreman 32 35<br />

Material costs<br />

Concrete 30 MPa (m 3 ) (1500m 3 job) 100 109<br />

Reinforcement bar 16mm (tonne) (120 tonne job) 880 957<br />

Concrete block (400x200) per 1000 (>10,000 block job) 600 652<br />

Standard brick per 1000 500 543<br />

Structural steel beams (tonne) (100 tonne+ job) 1,700 1,848<br />

Glass pane 10mm tempered (m 2 ) 225 245<br />

Softwood timber for framing 100mm x 50mm (m) 5 5<br />

13mm plasterboard (m 2 ) 5 5<br />

Emulsion paint (litre) 5 5<br />

Copper pipe 15mm (metre) (1000+ metre job) 6 7<br />

Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) 3 3.3<br />

Plant<br />

Hire 50t mobile crane + operator (day) 1,350 1,467<br />

Market:<br />

hot<br />

Tendering:<br />

warmer<br />

Cost escalation 2015–16: 6.0%<br />

Cost escalation <strong>2016</strong>–17: 6.0%<br />

Contractor’s margin: 5.0%<br />

Preliminaries: 10.0%<br />

Location factor (USD): 79<br />

PPP coefficient: 1.12<br />

<strong>International</strong> <strong>construction</strong> <strong>market</strong> <strong>survey</strong> <strong>2016</strong> 41