<strong>International</strong> building costs, in <strong>2016</strong><br />
SGD<br />
USD<br />
(exchange<br />
rate: 1.39)<br />
Retail<br />
Large shopping centre including mall 3,214 2,310<br />
Neighbourhood incl super<strong>market</strong> 2,107 1,520<br />
Prestige car showroom 3,380 2,430<br />
Composite trade rates<br />
Excavate basement (m 3 ) (1800m 3 job) 75 54<br />
Excavate footings (m) 25 18<br />
Concrete in slab (m 3 ) (1500m 3 job) 158 114<br />
Reinforcement in beams (tonne) 1,519 1,093<br />
Formwork to soffit of slab (m 2 ) 37 27<br />
Blockwork in wall (m 2 ) (10,000 block job) 65 47<br />
Structural steel beams (tonne) 4,018 2,891<br />
Pre-cast concrete wall (m 2 ) 142 102<br />
Curtain wall glazing incl support system (m 2 ) (1000m 2 job) 1,365 982<br />
Plasterboard 13mm thick to stud wall (m 2 ) (3000m 2 job) 25 18<br />
Single solid core door incl frame and hardware (no) (50 door job) 845 608<br />
Painting to walls primer + 2 coats (m 2 ) 10 7<br />
Ceramic tiling (m 2 ) (1000m 2 job) 87 62<br />
Vinyl flooring to wet areas (m 2 ) (500m 2 job) 80 58<br />
Carpet medium tufted (m 2 ) (4500m 2 job) 63 45<br />
Lighting installation (m 2 ) (5000m 2 + job) 205 147<br />
Copper pipe 15mm to wall (m) (1000+ metre job) 28 20<br />
Fire sprinklers (per m 2 ) (5000m 2 job) 82 59<br />
Air conditioning incl main plant (m 2 ) (5000m 2 + job) 267 192<br />
Labour costs<br />
Group 1 Tradesman e.g. plumber, electrician 28 20<br />
Group 2 Tradesman e.g. carpenter, bricklayer 20 14<br />
Group 3 Tradesman e.g. carpet layer, tiler, plasterer 28 20<br />
General labourer 17 12<br />
Site foreman 28 20<br />
Material costs<br />
Concrete 30 MPa (m 3 ) (1500m 3 job) 108 78<br />
Reinforcement bar 16mm (tonne) (120 tonne job) 1,176 846<br />
Concrete block (400x200) per 1000 (>10,000 block job) 700 504<br />
Standard brick per 1000 350 252<br />
Structural steel beams (tonne) (100 tonne+ job) 2,156 1,551<br />
Glass pane 10mm tempered (m 2 ) 120 86<br />
Softwood timber for framing 100mm x 50mm (m) 12 9<br />
13mm plasterboard (m 2 ) 8 6<br />
Emulsion paint (litre) 18 13<br />
Copper pipe 15mm (metre) (1000+ metre job) 13 10<br />
Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) 2 1<br />
Plant<br />
Hire 50t mobile crane + operator (day) 2,000 1,439<br />
Market:<br />
lukewarm<br />
Tendering:<br />
cooler<br />
Cost escalation 2015–16: 0.0%<br />
Cost escalation <strong>2016</strong>–17: 1.0%<br />
Contractor’s margin: 5.0%<br />
Preliminaries: 8.0%<br />
Location factor (USD): 59<br />
PPP coefficient: 1.29<br />