<strong>International</strong> building costs, in <strong>2016</strong><br />
Metric<br />
(m 2 )<br />
USD<br />
US Standard<br />
(ft 2 )<br />
Retail<br />
Large shopping centre including mall 3,658 340<br />
Neighbourhood incl super<strong>market</strong> 1,829 170<br />
Prestige car showroom 3,128 291<br />
Composite trade rates<br />
Excavate basement (m 3 ) (1800m 3 job) 38 29<br />
Excavate footings (m) 37 11.28<br />
Concrete in slab (m 3 ) (1500m 3 job) 300 229<br />
Reinforcement in beams (tonne) 2,000 1,814<br />
Formwork to soffit of slab (m 2 ) 90 8<br />
Blockwork in wall (m 2 ) (10,000 block job) 250 23<br />
Structural steel beams (tonne) 6,000 5,443<br />
Pre-cast concrete wall (m 2 ) 275 26<br />
Curtain wall glazing incl support system (m 2 ) (1000m 2 job) 1,800 167<br />
Plasterboard 13mm thick to stud wall (m 2 ) (3000m 2 job) 90 8<br />
Single solid core door incl frame and hardware (no) (50 door job) 2,250 2,250<br />
Painting to walls primer + 2 coats (m 2 ) 20 2<br />
Ceramic tiling (m 2 ) (1000m 2 job) 165 15<br />
Vinyl flooring to wet areas (m 2 ) (500m 2 job) 100 9<br />
Carpet medium tufted (m 2 ) (4500m 2 job) 63 53<br />
Lighting installation (m 2 ) (5000m 2 + job) 155 14<br />
Copper pipe 15mm to wall (m) (1000+ metre job) 55 17<br />
Fire sprinklers (per m 2 ) (5000m 2 job) 57 5<br />
Air conditioning incl main plant (m 2 ) (5000m 2 + job) 465 43<br />
Labour costs<br />
Group 1 Tradesman e.g. plumber, electrician 102 102<br />
Group 2 Tradesman e.g. carpenter, bricklayer 87 87<br />
Group 3 Tradesman e.g. carpet layer, tiler, plasterer 78 78<br />
General labourer 77 77<br />
Site foreman 130 130<br />
Material costs<br />
Concrete 30 MPa (m 3 ) (1500m 3 job) 147 112<br />
Reinforcement bar 16mm (tonne) (120 tonne job) 1,100 998<br />
Concrete block (400x200) per 1000 (>10,000 block job) 1,300 1,300<br />
Standard brick per 1000 561 561<br />
Structural steel beams (tonne) (100 tonne+ job) 2,512 2,279<br />
Glass pane 10mm tempered (m 2 ) 242 22<br />
Softwood timber for framing 100mm x 50mm (m) 5 1.60<br />
13mm plasterboard (m 2 ) 10 0.95<br />
Emulsion paint (litre) 7 27.03<br />
Copper pipe 15mm (metre) (1000+ metre job) 12 3.80<br />
Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) 6 1.87<br />
Plant<br />
Hire 50t mobile crane + operator (day) 3,600 3,600<br />
Market:<br />
overheating<br />
Tendering:<br />
staying the same<br />
Cost escalation 2015–16: 4.2%<br />
Cost escalation <strong>2016</strong>–17: 4.5%<br />
Contractor’s margin: 7.0%<br />
Preliminaries: 12.5%<br />
Location factor (USD): 127<br />
PPP coefficient: 2.23<br />