International construction market survey 2016
ebP5dMy
ebP5dMy
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>International</strong> building costs, in <strong>2016</strong><br />
MYR<br />
USD<br />
(exchange<br />
rate: 4.34)<br />
Retail<br />
Large shopping centre including mall 4,882 1,120<br />
Neighbourhood incl super<strong>market</strong> 4,161 960<br />
Prestige car showroom 5,305 1,220<br />
Composite trade rates<br />
Excavate basement (m 3 ) (1800m 3 job) 35 8<br />
Excavate footings (m) 50 12<br />
Concrete in slab (m 3 ) (1500m 3 job) 288 66<br />
Reinforcement in beams (tonne) 4,069 938<br />
Formwork to soffit of slab (m 2 ) 39 9<br />
Blockwork in wall (m 2 ) (10,000 block job) 70 16<br />
Structural steel beams (tonne) 10,000 2,304<br />
Pre-cast concrete wall (m 2 ) 233 54<br />
Curtain wall glazing incl support system (m 2 ) (1000m 2 job) 1,009 232<br />
Plasterboard 13mm thick to stud wall (m 2 ) (3000m 2 job) 130 30<br />
Single solid core door incl frame and hardware (no) (50 door job) 1,150 265<br />
Painting to walls primer + 2 coats (m 2 ) 10 2<br />
Ceramic tiling (m 2 ) (1000m 2 job) 150 35<br />
Vinyl flooring to wet areas (m 2 ) (500m 2 job) 217 50<br />
Carpet medium tufted (m 2 ) (4500m 2 job) 97 22<br />
Lighting installation (m 2 ) (5000m 2 + job) 162 37<br />
Copper pipe 15mm to wall (m) (1000+ metre job) 47 11<br />
Fire sprinklers (per m 2 ) (5000m 2 job) 118 27<br />
Air conditioning incl main plant (m 2 ) (5000m 2 + job) 309 71<br />
Labour costs<br />
Group 1 Tradesman e.g. plumber, electrician 31 7<br />
Group 2 Tradesman e.g. carpenter, bricklayer 20 5<br />
Group 3 Tradesman e.g. carpet layer, tiler, plasterer 23 5<br />
General labourer 10 2<br />
Site foreman 56 13<br />
Material costs<br />
Concrete 30 MPa (m 3 ) (1500m 3 job) 258 59<br />
Reinforcement bar 16mm (tonne) (120 tonne job) 3,800 876<br />
Concrete block (400x200) per 1000 (>10,000 block job) 3,500 806<br />
Standard brick per 1000 422 97<br />
Structural steel beams (tonne) (100 tonne+ job) 8,696 2,004<br />
Glass pane 10mm tempered (m 2 ) 775 179<br />
Softwood timber for framing 100mm x 50mm (m) 15 3<br />
13mm plasterboard (m 2 ) 28 6<br />
Emulsion paint (litre) 28 6<br />
Copper pipe 15mm (metre) (1000+ metre job) 29 7<br />
Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) 16 3.8<br />
Plant<br />
Hire 50t mobile crane + operator (day) 1,800 415<br />
Market:<br />
hot<br />
Tendering:<br />
cooler<br />
Cost escalation 2015–16: 3.0%<br />
Cost escalation <strong>2016</strong>–17: 3.0%<br />
Contractor’s margin: 12.5%<br />
Preliminaries: 10.0%<br />
Location factor (USD): 42<br />
PPP coefficient: 2.75<br />
<strong>International</strong> <strong>construction</strong> <strong>market</strong> <strong>survey</strong> <strong>2016</strong> 45