scheduled the drilling of two exploration wells<br />

OZW-1 and OZW-2. Preparations for the drilling<br />

platform of OZW-1 well are underway. The first<br />

well will be drilled in early 2009 in an effort to<br />

test the Jurassic objectives, in the Western<br />

Prerif basin ; simultaneously, a new ADD-HR<br />

campaign of 605 measure stations coupled<br />

with an additional geochemical survey, aimed at<br />

exploring other potential zones in these permits,<br />

is underway.<br />

Asilah permits (TransAlantic / Direct /<br />

Anschutz / Longe)<br />

Towards the end of <strong>2008</strong>, these partners<br />

acquired a new 2D seismics coverage totaling<br />

200.5 km. The processing of these data is<br />

underway.<br />

Gharb Centre and Gharb Sud permits (Cabre)<br />

Exploration works in the region included the<br />

acquisition and processing of 210 km of<br />

new 2D seismics aimed at highlighting new<br />

anomalies and specifying some gas prospects.<br />

Fès permit (Cabre)<br />

As part of its commitments over this permit,<br />

Cabre Company started, on 26 September<br />

16<br />

<strong>Office</strong> <strong>National</strong> <strong>des</strong> <strong>Hydrocarbures</strong> <strong>et</strong> <strong>des</strong> <strong>Mines</strong><br />

<strong>2008</strong>, the drilling of FES-1 well. As of December<br />

31, <strong>2008</strong>, the drilling has reached a depth of<br />

2 807 m at the level of a Miocene series. Gas<br />

shows have been encountered at the level of<br />

this Tertiary sequence. The drilling will continue,<br />

in 2009, to reach the expected final depth of<br />

3 800 m.<br />

Moulay Bousselham permit (Heyco)<br />

A postmortem survey on MED-1 well was<br />

compl<strong>et</strong>ed and enabled to direct exploration<br />

works towards gas targ<strong>et</strong>s, at the level of post<br />

nappe Tertiary. In this regard, ONHYM and<br />

Heyco undertook new negotiations aimed at<br />

defining a minimum work program over this<br />

permit.<br />

Sebou permit (Circle Oil)<br />

Circle Oil acquired at the beginning of <strong>2008</strong> an<br />

additional 3D seismics of 90 sq km covering<br />

Sebou permit by 145 sq km of 3D seismic<br />

data. Likewise, the company conducted a<br />

2D seismic survey of 57 km on the same<br />

permit. The interpr<strong>et</strong>ation of 3D seismics led<br />

to the identification of more than 80 potential<br />

anomalies.<br />

The first wells ONZ-6 and CGD-9, drilled<br />

b<strong>et</strong>ween, 26 September and 19 October<br />

and b<strong>et</strong>ween 4 and 24 November <strong>2008</strong>,<br />

respectively, enabled to show mo<strong>des</strong>t biogenic<br />

gas accumulations. The recoverable reserves<br />

are under evaluation by long-term tests.<br />

The platform of the third well KSR-8, scheduled<br />

in <strong>2008</strong>, was prepared but the bad weather<br />

conditions postponed the start of the drilling<br />

until January 2009. Preparations of platforms of<br />

the three other wells were launched.