UNCLASSIFIED<br />

MODIFICATION TITLE: OE-538/BRC/RFDACS<br />

COST CODE L0080<br />

MODELS OF SYSTEMS AFFECTED:<br />

DESCRIPTION/JUSTIFICATION: Installation of OE-538/BRC<br />

DEVELOPMENT STATUS/MAJOR DEVELOPMENT MILESTONES:<br />

FINANCIAL PLAN: ($ in millions)<br />

Prior Yrs FY 02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 TC Total<br />

Qty $ Qty $ Qty $ Qty $ Qty $ Qty $ Qty $ Qty $ Qty $ Qty $ Qty $<br />

RDT&E 0.9 0.4 1.2<br />

PROCUREMENT:<br />

Kit Quantity<br />

24 33.4 6 4.3 7 6.0 8 5.9 22 13.4 18 8.6 15 7.6 0 0.0 0 0.0 2 7.0 102 86.1<br />

Installation Kits 11 0.4 4 0.2 6 0.2 2 0.1 11 0.4 0 0.0 0 0.0 0 0.0 0 0.0 34 1.3<br />

Installation Kits Nonrecurring<br />

(See Note 3)<br />

Equipment 24 33.4 6 4.2 7 5.7 8 5.8 22 13.0 18 8.6 15 7.6 0 0.0 0 0.0 2 7.0 102 85.2<br />

Equipment Nonrecurring<br />

(See Note 5)<br />

Engineering Change Orders 3.7 2.3 6.0<br />

Data<br />

Training Equipment<br />

Support Equipment<br />

(See Note 6) (See Note 6)<br />

Production Support 0.4 0.3 0.6 0.6 1.2 1.2 1.3 1.0 1.1 0.0 7.6<br />

Other (See Note 2) 1 0.6 2 1.2 2 1.8 3 2.8 4 5.0 11 11.1 14 13.4 16 15.5 14 14.6 9 16.8 76 82.7<br />

Other (DSA) 0.1 0.1 0.4 0.2 0.5 0.9 0.9 0.5 0.0 0.0 3.6<br />

Installation of Hardware (See Note 1) 17 2.9 6 1.2 6 0.9 6 0.9 8 1.0 21 2.9 16 2.2 11 1.6 0.0 0.0 2 0.2 93 13.8<br />

PRIOR YR EQUIP 17 2.9 17 2.9<br />

FY 01 EQUIP 6 1.2 6 1.2<br />

FY 02 EQUIP 6 0.9 6 0.9<br />

FY 03 EQUIP 6 0.9 6 0.9<br />

FY 04 EQUIP 8 1.0 8 1.0<br />

FY 05 EQUIP 21 2.9 21 2.9<br />

FY 06 EQUIP 16 2.2 16 2.2<br />

FY 07 EQUIP 11 1.6 11 1.6<br />

FY 08 EQUIP 0 0.0 0 0.0<br />

FY 09 EQUIP 0 0.0<br />

FY TC EQUIP 2 0.2 2 0.2<br />

TOTAL INSTALLATION COST 3.0 1.2 1.3 1.2 1.5 3.9 3.1 2.1 0.0 0.2 93 17.4<br />

TOTAL PROCUREMENT COST 37.8 7.1 9.5 10.4 21.0 24.8 25.5 22.3 17.9 24.0 102 200.3<br />

METHOD OF IMPLEMENTATION: ADMINISTRATIVE LEADTIME: 3 months PRODUCTION LEADTIME: 12 months<br />

CONTRACT DATES: FY 2002: May-02 FY 2003: Feb-03 FY 2004: Feb-04 FY 2005: Jan-05<br />

DELIVERY DATES: FY 2003: May-03 FY 2004: Feb-04 FY 2005: Feb-05 FY 2006: Jan-06<br />

FY 04 FY 05 FY 06<br />

FY 07<br />

INSTALLATION SCHEDULE: PY 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4<br />

INPUT 27 2 1 3 2 1 3 3 1 2 6 6 6 3 6 6 2<br />

OUTPUT 26 3 3 3 1 3 3 1 2 6 6 6 3 6 6 2<br />

February 2004<br />

FY 08<br />

FY 09<br />

INSTALLATION SCHEDULE: 1 2 3 4 1 2 3 4 TC TOTAL<br />

INPUT 1 5 4 1 2 93<br />

OUTPUT<br />

Notes/Comments:<br />

1 5 4 1 2 93<br />

1) Nine (9) OE-538/BRC units are assigned to a rotatable pool to accommodate equipment refurbishment and do not require installation kits or funding. Pool assets were procured as follows:<br />

one in FY00, one in FY03, one in FY05, two in FY06 and four in FY 07.<br />

2) RFDAC Procurements<br />

3) ACU install kits complete in FY 05; FY 06-FY 09 install kits included in RFDAC procurement.<br />

4) FY05 thru FY 09 costs reflect cancellation of iUHF Upgrade Program (PR-05).<br />

5) FY06 unit cost variance due to mix of OE-538 and RFDAC units being procured without inclusion of ACU variant.<br />

6) FY 08 and 09 Engineering Change Proposal (ECP) for GPS Anti-Jam Upgrade .<br />

7) Unit cost variance due to increased number of masts with ACU.<br />

Exhibit P-3a, Individual Modification Program<br />

Unclassified<br />

P-1 Shopping List-Item No 79 - 7 of 15 Classification