5.3 Foundation<br />

Camino Generators<br />

A solid foundation is required in order to transmit the forces generated by the SET<br />

Camino Generator to as large an area as possible.<br />

Advantageous foundations <strong>and</strong> suitable points of the vehicle bottom are the following:<br />

− solid steel plate (approx. 10 mm)<br />

− glued wooden plate<br />

− Screen printing plate min. 30 mm<br />

Avoid cavities below the foundation.<br />

Carefully screw the foundation to the base area.<br />

The generator has been s<strong>up</strong>plied with a machine frame at which vibration<br />

metal elements are mounted. The vibration metal elements<br />

prevent solid borne noise from transmission onto the vehicle.<br />

Dimensions of machine frame:*<br />

* (refer also to dimensional sheet <strong>and</strong> technical data)<br />

03-04-01 <strong>Installation</strong> of the SET Camino Generator 5-33