7.3.1 For initial <strong>start</strong> proceed as follows<br />
1. Turn key-operated switch in position „ 1 “.<br />
Camino Generators<br />
2. The control LED pre-glowing lights <strong>up</strong>, pre-glowing time approx. 15 sec.<br />
3. Pre-glowing LED extinguishes.<br />
4. Turn key-operated switch in position „ START “.<br />
Diesel engine of generator <strong>start</strong>s (<strong>start</strong> phase < 3-4 sec.).<br />
If the red LED<br />
high voltage<br />
• LED<br />
If the Diesel engine does not <strong>start</strong> immediately, wait for approx. 5 s<br />
<strong>and</strong> repeat <strong>start</strong>ing.<br />
- +<br />
- +<br />
„battery“ flashes, the generator does not s<strong>up</strong>ply a sufficiently<br />
„battery” changes from RED to GREEN :<br />
• Diesel engine reaches its rated speed.<br />
• Generator s<strong>up</strong>plies its rated voltage (230 Volt).<br />
• All monitoring LED light green.<br />
Prior to loading the generator by electrical consumers check the<br />
coolant level in the expansion vessel.<br />
Now the generator can be loaded with electrical consumers.<br />
Turn main switch* (mains/generator switch) in position „2“.<br />
• Connect the consumers<br />
(for loading refer to the nameplate).<br />
• Switch off the generator in case of unclear troubles.<br />
(refer also to operating manual/Failure, elimination of failures, repair)<br />
* (if any)<br />
Do not operate the generator continuously in short-time mode but<br />
mainly in continuous mode under load.<br />
(refer also to documents of engine manufacturer)<br />