<strong>2010</strong> -11 SHIP Targets<br />

5.3 • Total AHIP fund target - £5,341,000<br />

• Total unit approval target – 55 units:<br />

• 21 units at Bellsdyke Hospital site, Larbert,<br />

• 28 units at Overton, Redding,<br />

• 6 units at Bridge Street, Bonnybridge.<br />

• Total unit completion target – 119 units:<br />

• 30 units at Wood Street, Grangemouth (Complete),<br />

• 43 units at Torwoodlea, Larbert (Complete),<br />

• 20 units at Thorndene Terrace, Slamannan (Complete),<br />

• 16 units at Mayfield Drive, Longcroft (On-site),<br />

• 10 units at McTaggart Avenue, Denny (On-site).<br />

In addition to new affordable units delivered through the core AHIP, units will also<br />

be delivered via:<br />

<strong>Council</strong> new Build programme – 96 units:<br />

• 8 units at Sawers Avenue, (Complete),<br />

• 4 units at Carse Crescent, Laurieston (Complete),<br />

• 12 units at Chisholm Place, Grangemouth (On-site),<br />

• 10 units at Carron Road(Small site), Bainsford (On-site),<br />

• 20 units at Shiel Gardens, Langlees (On-site),<br />

• 18 units at Chequers, Hallglen (On-site),<br />

• 24 units at Cadzow Avenue, Bo’ness (Due on-site Dec <strong>2010</strong>).<br />

Existing supply with change of tenure to affordable housing - 18 units:<br />

• 8 units completed through the <strong>Council</strong>’s Mortgage to Rent scheme,<br />

• 2 units completed through the RSL Mortgage to Rent scheme,<br />

• 8 units completed through the OMSE scheme.<br />

Sawers Avenue, Denny Carse Crescent, Lauriston<br />

39