PILLARS - Key Strategic Activity<br />

Target Measure Status Comments<br />

Pillar 5. Transportation: Continue East/West Traffic improvement works<br />

Continue East/West Traffic<br />

Improvement works. Works<br />

listed for <strong>2007</strong>-<strong>2008</strong> are:<br />

> Mercer St / Gheringhap St /<br />

Malop St intersection<br />

> Ryrie St / Sydney Pde /<br />

Swanston St intersection<br />

> Garden St / Portarlington Rd<br />

intersection<br />

> Gheringhap St / Ryrie St<br />

intersection<br />

> Latrobe Tce clearway<br />

East/West Traffic improvement<br />

works listed for <strong>2007</strong>-<strong>2008</strong><br />

financial year to be completed<br />

by 30 June, <strong>2008</strong>.<br />

Of the five actions<br />

listed, two have<br />

been completed,<br />

two will be<br />

completed in July<br />

<strong>2008</strong> and one is<br />

yet to commence.<br />

Unspent funds to<br />

be carried over into<br />

<strong>2008</strong>-2009.<br />

Progress on <strong>2007</strong>-<strong>2008</strong> listed works:<br />

> Mercer St / Gheringhap St / Malop St intersection has been completed with the roundabout replaced by traffic signals.<br />

The restored Belcher Fountain has also been installed at the intersection.<br />

> Ryrie St / Sydney Pde / Swanston St intersection works commenced in April and is expected to be completed<br />

by mid-July <strong>2008</strong>.<br />

> Garden St / Portarlington Rd intersection works are in progress and due to be completed early in <strong>2008</strong>-2009.<br />

> Gheringhap St / Ryrie St intersection works have been deferred to <strong>2008</strong>-2009.<br />

> Latrobe Tce clearway has been completed.<br />

> Malop St / Fitzroy St intersection works were brought forward to <strong>2007</strong>-<strong>2008</strong> (originally programmed to be completed<br />

in <strong>2008</strong>-2009) and was completed in November <strong>2007</strong>.<br />

Pillar 6. Parks, Sport and Leisure: Goldsworthy Athletics Reserve terrace construction<br />

Goldsworthy Athletics Facility<br />

terrace construction<br />

Complete construction of<br />

terrace at Goldsworthy Athletics<br />

Facility by 30 June, <strong>2008</strong>.<br />

Project completed.<br />

Spectator terracing at Goldsworthy Athletics Reserve was completed.<br />

Pillar 7. Education and Research: Complete design and consultation and commence construction of the Vines Road Community Centre development<br />

Vines Road Community Centre<br />

development (in conjunction<br />

with the Education Department)<br />

Complete design, consultation<br />

and commence construction of<br />

Vines Road Community Centre<br />

by 30 June, <strong>2008</strong>.<br />

Design and<br />

consultation<br />

completed.<br />

Construction yet to<br />

commence.<br />

The outcome for the community of the Vines Road Community Centre redevelopment will be a new school complex which<br />

incorporates a wide range of community services and recreation facilities including a rebuilt community centre / senior citizens<br />

centre, netball courts, oval, library and a performing arts centre.<br />

The concept designs have been completed and consultation has taken place. Negotiations on agreements are continuing and<br />

once completed land will be sold, tender advertised and construction will commence under the management of the Department<br />

of Education and Early Childhood Development.<br />

Pillar 8. Arts, Culture and Heritage: Conduct Community Arts Grant Program<br />

Community Arts Grant Program<br />

Provide grants for community<br />

arts groups and activities during<br />

<strong>2007</strong>-<strong>2008</strong> as per budget.<br />

<strong>2007</strong>-<strong>2008</strong><br />

program<br />

completed.<br />

30 groups applied for a grant under the Community Arts Grant Program with 24 groups successful in receiving grants totalling<br />

$98,997. A grant ceremony was held in February <strong>2008</strong> to provide an opportunity to showcase the community projects as well<br />

as a networking opportunity for community groups.<br />

Pillar 9. Telecommunications: Replace Council’s ageing internal telephone system with Voice Over Internet Protocol communication system<br />

Council’s internal telephone<br />

system (PABX) replacement<br />

with Voice Over Internet<br />

Protocol communication system<br />

Replace Council’s internal<br />

telephone system (PABX) with<br />

Voice Over Internet Protocol<br />

communication system by 30<br />

June, <strong>2008</strong>.<br />

<strong>2007</strong>-<strong>2008</strong> project<br />

actions completed.<br />

All infrastructure has been installed and software has been upgraded and is in production. The extension of the system to make<br />

it hybrid and provide Voice Over IP capability has been installed and is operational. The four digit extension changeover has<br />

been scheduled to be completed in <strong>2008</strong>-2009.<br />