MEMORANDUM<br />

B. The <strong>Village</strong> requested CBBEL estimate costs associated with the retr<strong>of</strong>it <strong>of</strong> the existing<br />

lighting system along the segment <strong>of</strong> Kreutzer Road installed as part <strong>of</strong> the Lions Chase<br />

residential subdivision. CBBEL counted 27 existing streetlights along the existing segment<br />

<strong>of</strong> Kreutzer Road.<br />

27 fixtures x $1,300/each installed LED fixture retr<strong>of</strong>it kit = $35,100<br />

3 controllers to be modified with meters: 3 x $1,500 per controller<br />

(assumed) = $ 4,500<br />

Total estimated retr<strong>of</strong>it construction cost = $39,600<br />

ComEd one time rebate program savings (if available): 27 luminaires x<br />

$15 per fixture = ($ 405)<br />

DOE one time incentive program savings (if available): 27 luminaires x<br />

$15 per fixture = ($ 405)<br />

Total retr<strong>of</strong>it cost approximately = $39,000<br />

C. CBBEL recommends the <strong>Village</strong> consider the following issues related to the use <strong>of</strong> LED<br />

technology and to the retr<strong>of</strong>it <strong>of</strong> existing HPS streetlights to LED systems.<br />

<br />

The current rate <strong>of</strong> $0.03 per kW-hr that the <strong>Village</strong> pays for electrical service from<br />

Commonwealth Edison on the Rate 25 contracts is considered to be at the low end <strong>of</strong><br />

rates CBBEL typically sees with our other municipal clients.<br />

The overall age <strong>of</strong> the majority <strong>of</strong> the <strong>Village</strong>’s street lighting systems is plus or minus 10<br />

years. CBBEL approximated the <strong>Village</strong>’s average age <strong>of</strong> the street network to be 10<br />

years in our 2011 pavement evaluation report. Typical luminaire life should be<br />

considered to be 30+ years.<br />

<br />

<br />

The pace in which LED technology is evolving may mean current LED retr<strong>of</strong>it kits may<br />

be obsolete in the near future when replacement parts may be required for knock downs<br />

and miscellaneous physical damage.<br />

Following the retr<strong>of</strong>it <strong>of</strong> a <strong>Village</strong> street lighting system, the <strong>Village</strong> may have to stock<br />

additional LED retr<strong>of</strong>it kits in advance <strong>of</strong> possible maintenance repairs being identified.<br />

Having the material on hand would provide the ability to make timely repairs to the<br />

system to avoid long delays in obtaining replacement parts as LED parts are not stocked<br />

by local electrical supply houses as HPS and metal halide lamps are typically stocked.<br />

SOLAR POWERED STREET LIGHTING<br />

CBBEL is continuing to research and explore the options related to solar powered street lighting<br />

equipment. Please find attached a brochure CBBEL was able to obtain from a manufacture <strong>of</strong> a<br />

solar / wind powered lighting equipment.<br />

GJS/gjs/pjb<br />

N:\<strong>Huntley</strong>\070103\070103.00040\Admin\M1.042313Revised.docx<br />

Page 3 <strong>of</strong> 3<br />

CHRISTOPHER B. BURKE ENGINEERING, LTD.<br />

9575 W Higgins Road, Suite 600 Rosemont, Illinois 60018-4920 Tel (847) 823-0500 Fax (847) 823-0520