Task 5 - Material Inspection: CBBEL will perform the following tasks further described in<br />
the attached proposal from Testing Service Corporation:<br />
• CBBEL will utilize Testing Service Corporation (TSC) for the material testing portions<br />
<strong>of</strong> this contract. In accordance with federally funded projects, Testing Service<br />
Corporation will provide Quality Assurance (QA) testing on-site as outlined by I DOT's<br />
Bureau <strong>of</strong> Material and Physical Research, and further described in the Construction<br />
Manual and Project Procedures Guide. lOOT is responsible for QA testing at the<br />
concrete and HMA plants.<br />
• The Resident Engineer provided by CBBEL will be familiar with the frequency <strong>of</strong> QA<br />
testing as required by lOOT as outlined in their Project Procedures Guide. The<br />
Resident Engineer will coordinate the QA material testing and review all required<br />
reports submitted by both the Contractor's QC sub-contractor and TSC for<br />
compliance with the project specifications.<br />
Task 6 - Record Drawings: CBBEL will perform the following tasks:<br />
• Modify contract drawings to reflect as-built conditions. The record drawings<br />
should be revised to depict field measurements <strong>of</strong> the completed work which is<br />
considered significant and provide the <strong>Village</strong> with the record plan submittal and<br />
all equipment operation/maintenance manuals within ninety (90) days <strong>of</strong> the<br />
project completion. Submittals shall include but are not limited to:<br />
• Two (2) full-size (24"x36") paper print record plan sets.<br />
• One (1) CD containing an electronic submittal <strong>of</strong> the as-built plans (.pdf format).<br />
Task 7 - Project Documentation: CBBEL will perform the following tasks:<br />
• In general, all documentation will be completed following lOOT's Construction<br />
Manual and Project Procedures Guide. The ICORS and MISTIC s<strong>of</strong>tware programs<br />
will be used for documentation and material RE Visuals, respectively.<br />
• Make all diary entries in ICORS recording Contractor hours on the job site, weather<br />
conditions, general and specific observations, daily activities, list <strong>of</strong> visiting <strong>of</strong>ficials,<br />
and documentation <strong>of</strong> the "traffic control drive-thru check" as outlined in the<br />
Construction Manual. Generate weekly reports using ICORS for distribution to I DOT,<br />
the <strong>Village</strong>, and the Contractor.<br />
• Prepare Change Orders and Pay Estimates using lOOT's ICORS s<strong>of</strong>tware for the<br />
<strong>Village</strong>'s approval.<br />
• Review and coordinate response to any RFI from the Contractor in a timely manner<br />
and maintain a separate file for each request.<br />
• Complete daily reports recording and documenting the quantities completed. All<br />
quantities shall be documented following the I DOT Construction Manual.<br />
GJS/gjs Page 4 <strong>of</strong> 6<br />
N:\PROPOSALS\ADMIN\2013\<strong>Huntley</strong>- Kreutzer Road.050313.doc