Proposal Review Detail • Category Continues ..<br />
Job Order Number: 015225.00<br />
Job Order Title: <strong>Village</strong> <strong>of</strong> <strong>Huntley</strong>- aerobic digester blowers<br />
Rec# CSI Number Mod. UOM Description<br />
Line Total<br />
Electric<br />
17<br />
26 OS 33 00 0481 EA 1-1/4" RGS 90 Degree Elbow<br />
Quantity<br />
Installation<br />
4.00 X<br />
Contractors Note: Conduit elbows.<br />
Unit Price<br />
37.66<br />
X<br />
Factor<br />
1.0100<br />
Total<br />
$152.15<br />
$152.15<br />
18<br />
26 05 33 00 0484 EA 2-1/2" RGS 90 Degree Elbow<br />
Quantity<br />
Installation<br />
4.00 X<br />
Contractors Note: Concuit elbows.<br />
Unit Price<br />
73.95<br />
X<br />
Factor<br />
1.0100<br />
Total<br />
$298.76<br />
$298.76<br />
19<br />
26 05 33 00 0533 EA 1-1/4" RGS Box Connector, Insulated With Set Screw<br />
Quantity<br />
Unit Price<br />
Installation 4 . 00 x 21.36 x<br />
Factor<br />
1.0100<br />
Total<br />
$86.29<br />
$86.29<br />
Contractors Note: Conduit box connectors<br />
20<br />
26 05 33 00 0536 EA 2-1/2" RGS Box Connector, Insulated IMth Set Screw<br />
Quantity<br />
Unit Price<br />
Installation 6.00 X 80.98 X<br />
Factor<br />
1.0100<br />
Total<br />
$490.74<br />
$490.74<br />
Contractors Note: Conduit box connectors<br />
21<br />
26 05 33 00 2499 EA<br />
12nx12Hx12~ Cast Iron Pull Box With Cover<br />
Installation<br />
Quantity<br />
1.00 X<br />
Unit Price<br />
321.14 X<br />
Contractors Note: Pull box installed on ceiling <strong>of</strong> electric building for new conduit.<br />
Factor<br />
1.0100<br />
Total<br />
$324.35<br />
$324.35<br />
22 26 24 19 00 0027 EA 480V Full Vo!t, 1 Speed, Reversing, 100 HP Combination With Molded Case<br />
Circuit<br />
Quantity Unit Price Factor<br />
Installation<br />
2.00 X 4,589.79 X 1.0100<br />
Demolition 2.00 X 90.67 X 1.0100<br />
Total<br />
$9,271.38<br />
Contractors Note: Remove two existing buckets, and install two new buckets for VFD's in existing gear with main breaker for<br />
each.<br />
$183.15<br />
$9,454.53<br />
23<br />
26 28 16 00 0183 EA 200 A Fused Disconnect Switch, NEMA 3R, Heavy Duty, With Fuses, 600 V, 3<br />
Phase<br />
Installation<br />
Quantity<br />
2.00 X<br />
Unit Price<br />
1,607.88 X<br />
Factor<br />
1.0100<br />
Contractors Note: Exterior weatherpro<strong>of</strong> disconnects for new blowers.<br />
Total<br />
$3,247.92<br />
$3,247.92<br />
24<br />
40 92 49 00 0001 EA 75 HP Variable Frequency Drive, 460 V 3 PH, including ventilated NEMA 12<br />
Enclosure<br />
NPPTask<br />
Quantity<br />
Unit Price<br />
Factor<br />
Installation<br />
2.00 X 14,397.50 X<br />
1.0500<br />
Total<br />
$30,234.75<br />
Contractors Note: Supply two 75 HP VFD's with ventilated NEMA 12 enclosures. Quoted from same supplier that is supplying<br />
blowers to <strong>Huntley</strong>. These VFD's are specific to the blower units ordered by <strong>Huntley</strong>. Material cost only.<br />
$30,234.75<br />
25<br />
40 92 49 00 0029<br />
EA<br />
75 HP, 480Volt Variable Frequency Drive Wall mounted.<br />
$2,036.64<br />
Exetudes<br />
Materlaf<br />
Quantity<br />
Unit Price<br />
lnsta1tation 2 .00 x 1,008.24 x<br />
Factor<br />
1.0100<br />
Total<br />
$2,036.64<br />
Contractors Note: Labor cost to Install two VFD's In mechanical building.<br />
Subtotal for Electric: $68,134.70<br />
Mechanical<br />
Proposal Review Detail ~ Category<br />
Page 3<strong>of</strong>6<br />
4/25/2013