Tender No.<br />
S&T/BRC/12-13/03 (Signal)<br />
DOWN LOADED FROM INTERNET<br />
4.6 CONSIGNEE<br />
The consignee for this work of will be Senior Section Engineer (Signal) /<br />
Nadiad.<br />
4.7 WORK TO BE DONE BY THE RAILWAYS<br />
(a) FOLLOWING SHALL BE DONE BY RAILWAYS<br />
(i)<br />
Statuary Testing of installation/equipments (as per SEM) shall be done<br />
under supervision of <strong>Railway</strong> officials or by <strong>Railway</strong> officials themselves,<br />
once contractor offers installation is ready commissioning in all respect.<br />
The electric supply for this purpose will be provided by the <strong>Railway</strong>s.<br />
However, for any installation activities like drilling, soldering etc.,<br />
contractor if so desires, to use tools / machines, electric power supply<br />
(230V) can be arranged by <strong>Railway</strong>s as per extant procedure.<br />
(b) MATERIAL TO BE PROVIDED BY RAILWAYS<br />
(i)<br />
(ii)<br />
Supply of Signalling Plan of the Stations/ yard.<br />
Two Aspect colour light signal unit.<br />
(iii) LED Signal Lighting units for Main Signals & Shunt Signals.<br />
(iv) PVC insulated, armoured, unscreened and underground <strong>Railway</strong><br />
Signalling cables as per RDSO specification.<br />
12 core X 1.5 Sq. mm,<br />
(v)<br />
Underground <strong>Railway</strong> jelly filled 6 Quad cable as per RDSO<br />
Specification.<br />
(vi) 2 core x 25 sq.mm. aluminum power cable as per Specn. IS:1554 Part<br />
I. Insulation resistance conforming to IRS(S)-63/2007.<br />
(vii) In case above cables mentioned are not available, other types of cable<br />
will be provided as per the decision of the Engineer-in-charge.<br />
(viii) Any other materials required to be supplied by <strong>Railway</strong>s as per<br />
Technical Requirement and Specification and schedule of material &<br />
works.<br />
4.8 WORKS REQUIRED TO BE DONE BY THE CONTRACTOR<br />
(i)<br />
(ii)<br />
Design of Circuits and plans to suit layout given in the signalling plan.<br />
Preparation of Completion documents on standard 75 micron polyester film.<br />
(iii) Guarantee period will be one year from date of commissioning. Any defect<br />
noticed during this period will have to be rectified by contractor promptly at<br />
his own cost.<br />
(iv) The cost of transit insurance required as per rules will be borne by the<br />
contractor.<br />
For Sr. Divisional Signal & Telecom Engineer Page 20 of 68 Signature of Tenderer & Seal<br />
For and on behalf of President of India