Tender No.<br />

S&T/BRC/12-13/03 (Signal)<br />

DOWN LOADED FROM INTERNET<br />

Extension of time on <strong>Railway</strong> account:<br />

(a) In the event of any failure or delay by the <strong>Railway</strong> to hand over site /<br />

signalling plans to the contractor necessary for the execution of the works or<br />

to provide the necessary drawings or instructions or any other delay caused<br />

by the <strong>Railway</strong> due to any other cause whatsoever, then such failure or delay<br />

shall in no way affect or vitiate the contract or alter the character or entitle the<br />

contractor to damage or compensation thereof but in any such case, the<br />

<strong>Railway</strong> may grant such extension of the completion date as may be<br />

considered reasonable.<br />

(b) If the progress of the work be delayed at any time in the progress of the work<br />

by any act of neglect of the <strong>Railway</strong>‘s employee or by any other contractor<br />

employed by the <strong>Railway</strong> or by strike, lockouts, fire, unusual delay in<br />

transportation, unavoidable casualties or any cause beyond the contractor‘s<br />

control, or any delay authorized by the <strong>Railway</strong> Engineer, the time of<br />

completion of the work may be extended for such reasonable time as the<br />

<strong>Railway</strong> administration may decide.<br />

Liquidated Damages & <strong>Railway</strong>‟s rights:<br />

The time for completion of the work by the date or extended date fixed for<br />

completion shall be deemed to be the essence of the contract and if the<br />

contractor shall fail to complete the work within the time prescribed, action<br />

will be taken as per Clause 17-B of GCC. If the <strong>Railway</strong> is not satisfied that<br />

the work can be completed by the contractor to within the further extension of<br />

time allowed as aforesaid, the <strong>Railway</strong> shall be entitled without prejudice to<br />

award any other contract under Clause 62 of General Conditions of the<br />

contract whether or not actual damage is caused by such default.<br />

4.42 DETERMINATION OF CONTRACT<br />

The Contractor shall execute the work with due diligence and expedition, keeping<br />

to the approved time schedule. Should he refuse or neglect to comply with any<br />

reasonable order given to him in writing by the Purchaser‘s Engineers in<br />

connection with the work lags persistently behind the time schedule due to his<br />

neglect, the <strong>Railway</strong> shall at liberty to give seven days notice in writing to the<br />

Contractor requiring him to make good the neglect or contravention complained<br />

of and should the contractor fail to comply with the requisitions made in the<br />

notice within seven days from the receipt thereof, it shall be lawful for the<br />

purchaser to take action as per clause 62 of GCC and to take the work wholly or<br />

in part out of the Contractor‘s hands without any further reference and get the<br />

work or any part thereof, as the case may be, completed by other agencies at<br />

the expense of the contractor without prejudice to any other right or remedy of<br />

the Purchaser.<br />

4.42.1 LOSS SUSTAINED DUE TO DEFAULT AND DELAY<br />

In the event of any loss to the <strong>Railway</strong>s on account of execution and/or delay in<br />

completion of the work or any part thereof by agencies other than the contractor,<br />

the contractor shall be liable to reimburse the loss to <strong>Railway</strong>s without prejudice<br />

to the other rights and remedies of the purchaser, and the reimbursement in full<br />

or in part as the case may be, shall be met, at the option of the <strong>Railway</strong>s from out<br />

of all or any of the following sources viz:<br />

For Sr. Divisional Signal & Telecom Engineer Page 42 of 68 Signature of Tenderer & Seal<br />