1.1 TECHNICAL ASSESSMENT AND SAFETY AUDIT<br />
1.1.1 INTRODUCTION AND SUMMARY OF PROCESS<br />
Any works undertaken on the highway and/or which will form part of<br />
the adopted highway network will require adoption approval from<br />
the <strong>Kent</strong> <strong>County</strong> <strong>Council</strong> or Medway <strong>Council</strong> (the two Highway<br />
Authorities in <strong>Kent</strong>). The individual, firm, organisation (or their<br />
representative) who wishes physically to alter the highway is called<br />
‘The Scheme Promoter’. To ensure an acceptable scheme is built, all<br />
schemes must undergo a technical assessment and safety audit<br />
process carried out either by the Highway Authority, or District<br />
Authority (Highway Unit), acting as authorised representative,<br />
depending on the scale of the scheme.<br />
Although <strong>Technical</strong> Appraisal and Safety Audit procedures are dealt<br />
with in a similar manner in the Medway <strong>Council</strong> Authority it will be<br />
necessary to follow their latest guidelines. The following guidance is<br />
relevant to schemes in all parts of the county but requests for<br />
detailed advice, queries and correspondence relating to schemes in<br />
Medway should be directed to Medway <strong>Council</strong>.<br />
For schemes in the rest of the county the KCC Highway Authority<br />
will conduct the technical assessment and safety audit process for<br />
schemes that require a Section 278 agreement valued in excess of<br />
£25000, and schemes that have county wide significance constructed<br />
under a Section 38 agreement. The Scheme Promoter will be advised<br />
by the <strong>County</strong> <strong>Council</strong> whether or not proposals will have county<br />
wide significance.<br />
Schemes constructed under Section 38 agreements that do not have<br />
county wide significance are technically assessed and safety audited<br />
by the District Authority Highway Unit (HU) prior to adoption by the<br />
KCC Highway Authority. Similarly, schemes involving Section 278<br />
agreements valued at less than £25000 are assessed and audited by<br />
the Highway Unit.<br />
CONCEPT AND FEASIBILITY OF SCHEME -<br />
The scale of the proposals and the resultant effect on the public<br />
highway will need to be discussed in collaboration with the<br />
appropriate Highway Unit (HU) or Area Office (West, Mid or North-<br />
East) of KCC’s Network Management Unit. Once the nature and<br />
feasibility of the scheme is accepted by the appropriate authority,<br />
(KCC Area Office or HU), the scheme will be formally assessed at<br />
the three stages of the scheme’s life, the preliminary/outline design<br />
stage, the detail design stage and the construction stage. It is<br />
envisaged that this process will run alongside other legal, planning and<br />
technical requirements. If a scheme is not progressed to the next<br />
stage of its assessment within 24 months it will need to be resubmitted<br />
at the start of the process.<br />
Schemes which include a new structure or a modification to an<br />
existing structure will require KCC structures technical approval (see<br />
Section 1.1.5).<br />
Following the broad acceptance of the concept, the Scheme<br />
Promoter will receive written confirmation from the Area Office/HU<br />
of this, detailing any specific requirements and agreements, together<br />
with guidance on how to proceed. This may include<br />
recommendations to submit a design using a design consultant on an<br />
approved list.<br />
GUIDANCE NOTES FOR SCHEME PROMOTERS -<br />
Outline <strong>Design</strong> <strong>Technical</strong> Assessment and Safety Audit (Stage<br />
1) of the overall process - Once the principle of the scheme has<br />
<strong>Kent</strong><br />
<strong>Design</strong><br />
been agreed, then unless otherwise stated by the Area Office/HU,<br />
the next part of the process will be to produce an acceptable outline<br />
design and this will be subject to various technical checks and a safety<br />
audit report. In the case of schemes requiring planning permissions<br />
or associated with planning applications, this should be prior to or as<br />
soon as practical after the granting of planning permission. It is<br />
recommended that the Scheme Promoter has informal discussions<br />
with the HU or KCC Area Office at the preliminary stages in order<br />
to ensure that the proposals will result in the safest and most<br />
appropriate layout for that site.<br />
The Scheme Promoter must submit the appropriate documentation<br />
for the outline design technical assessment and safety audit within 24<br />
months of the principle of the scheme being accepted. The Area<br />
Office/HU should within 6 working days of receipt, provide a contact<br />
name and acknowledge receipt of the submission or return<br />
unsuitable submissions. Provided an acceptable submission is<br />
received by the Area Office/HU, then the Scheme Promoter should<br />
receive a response and assessment from the Area Office/HU no later<br />
than six weeks after receiving written acknowledgement of receipt of<br />
the scheme at the Area Office/HU. Where this target cannot be met<br />
the Scheme Promoter will be informed of the circumstances. The<br />
Scheme Promoter will then either be given guidance as to whether<br />
the scheme needs to be resubmitted at the outline stage, or guidance<br />
on producing a submission for the detailed design technical<br />
assessment and safety audit part of the procedure. This may be<br />
subject to various conditions. Any approvals given at this stage of the<br />
process must not be considered as approval to construct the scheme.<br />
Detail <strong>Design</strong> <strong>Technical</strong> Assessment and Safety Audit (Stage<br />
2) of the overall process - The Scheme Promoter will have<br />
received guidance from the Area Office/HU on how to proceed to<br />
the detail design technical assessment and safety audit part of the<br />
overall scheme process. It may be possible in the case of some small<br />
schemes to submit Stages 1 and 2 combined. Advice on this must be<br />
sought from the relevant authority. On receipt of the detailed design<br />
submission, the Area Office/HU should, within 6 working days<br />
provide a contact name and acknowledge receipt of the submission,<br />
or return unsuitable submissions. The designated contact in liaison<br />
with the Area Office/HU will discuss and agree the time scale to<br />
assess the scheme. Any requirements as a result of a preliminary<br />
assessment of the detail design may be discussed. Once an<br />
acceptable detail design has been agreed, and subject to other legal<br />
and technical issues the Scheme Promoter will receive written<br />
approval to start construction from the Area Office/HU (or<br />
designated representative), which may be subject to various<br />
conditions. Guidance regarding site supervision, inspections and an<br />
as-built safety audit may also be provided.<br />
As Built (Stage 3) of the overall process - Once the scheme is<br />
substantially completed an inspection may be required as well as an<br />
as-built safety audit. The Scheme Promoter (or designated<br />
representative) will need to inform the Area Office/HU in writing<br />
when the Scheme is ready to be inspected and safety audited. It<br />
should be noted that the safety audit will normally be carried out<br />
separately from other inspections. At this stage of the process it is<br />
not envisaged that major changes will take place. It does provide an<br />
opportunity to identify potential safety issues not previously detected<br />
in the design process, for whatever reason. Liability for rectifying any<br />
potential hazards as identified and requested by the Area Office/HU<br />
or authorised representative is the responsibility of the Scheme<br />
Promoter.