18.06.2014 Views

Appendix F Detailed Cover Type Tables - USDA Rural Development

Appendix F Detailed Cover Type Tables - USDA Rural Development

Appendix F Detailed Cover Type Tables - USDA Rural Development

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Bemidji – Grand Rapids<br />

Biological Assessment and Evaluation<br />

2.3.3 Alternatives<br />

Through the evaluations completed to date, the Applicants have identified three routes that could meet<br />

the Project purpose and need, as well as a number of alternative segments and crossovers (Figure 2 –<br />

Project Alternatives). The route widths are generally 1,000 feet or greater. The actual transmission line<br />

would only require a 125‐foot‐wide right‐of‐way (ROW). These 1,000‐foot‐wide routes will be used to<br />

identify a 125‐foot ROW within which the transmission line would be constructed, and do not represent<br />

the total footprint of the alternatives. The final centerline and ROW will be identified after the route is<br />

selected through the environmental review and permitting process.<br />

Ancillary facilities necessary to support the project include new or upgraded substations and a breaker<br />

station. Each of the routes and ancillary facilities are described below.<br />

Route 1 generally follows the Great Lakes Gas Transmission Company (Great Lakes) pipeline right‐ofway<br />

from the Wilton Substation to just east of Deer River, where it then follows a Minnesota Power<br />

115 kV transmission line to the Boswell Substation.<br />

Route 2 generally follows U.S. Highway 2 (US 2) and the pipeline rights‐of‐way of Enbridge Pipelines LLC<br />

(Enbridge) for its entire length between the Wilton Substation and Boswell Substation.<br />

Route 3 bypasses the LLR by taking a more northerly route between Bemidji and Grand Rapids. This<br />

route generally parallels existing transmission line rights‐of‐way between Bemidji, Blackduck, Deer River,<br />

and Grand Rapids. Route 3 passes though the CNF in Itasca and Beltrami counties.<br />

Route options 1A, 1B, 1C, and 2C represent bypass routes that connect sections of Routes 1 and 2, and<br />

are intended to allow opportunities for connections between portions of the primary routes in order to<br />

avoid sensitive environmental resources.<br />

Certain upgrading of the Wilton Substation near Bemidji and the Boswell Substation near Grand Rapids<br />

would be required, as well as upgrading an existing 115 kV substation or building a new 230 kV<br />

substation in the Cass Lake area. Depending on the route selected, a breaker station may also be<br />

constructed at Nary Junction. The upgrades and proposed new construction are discussed below.<br />

Wilton Substation – The Project would not require physical expansion of the existing Wilton 230 kV<br />

Substation. Two new 230 kV breakers and a line termination structure would be added as a result of the<br />

Project, along with modifications to the existing 230 kV buses and relay panels. The Project would also<br />

require completion of a new ring bus section, as well as five new 230 kV switches with foundations, steel<br />

structures, and control panels.<br />

Boswell Substation – The Project would require the expansion of the Boswell 230 kV Substation by<br />

approximately 1.3 acres. No land procurement is required, however, because the entire expansion of<br />

the substation would be on Minnesota Power‐owned property. In addition to modifications to the<br />

existing 230 kV buses and relay panels, a new 230 kV breaker and a half bay would be added to the<br />

substation. This would involve installing two new 230 kV circuit breakers and 230 kV dead‐end<br />

structures, a new 230 kV bus, five new 230 kV switches, and associated foundations, steel structures,<br />

and control panels.<br />

Cass Lake Area Substation – The Project would require the expansion of the existing Cass Lake<br />

115/69 kV Substation or construction of a new 230/115 kV substation, depending on which route is<br />

selected. Routes 2 and 2C would require upgrading of the existing Cass Lake Substation. This would be<br />

accomplished by extending the existing fence line approximately 320 feet west. No land procurement<br />

would be required because the expansion of the substation would be on existing Otter Tail<br />

Power‐owned property. The expansion would be for the 230 kV equipment, which includes a 230 kV<br />

July 2010 Description of the Proposed Action Page 2‐4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!