Appendix F Detailed Cover Type Tables - USDA Rural Development
Appendix F Detailed Cover Type Tables - USDA Rural Development
Appendix F Detailed Cover Type Tables - USDA Rural Development
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Bemidji – Grand Rapids<br />
Biological Assessment and Evaluation<br />
2.3.3 Alternatives<br />
Through the evaluations completed to date, the Applicants have identified three routes that could meet<br />
the Project purpose and need, as well as a number of alternative segments and crossovers (Figure 2 –<br />
Project Alternatives). The route widths are generally 1,000 feet or greater. The actual transmission line<br />
would only require a 125‐foot‐wide right‐of‐way (ROW). These 1,000‐foot‐wide routes will be used to<br />
identify a 125‐foot ROW within which the transmission line would be constructed, and do not represent<br />
the total footprint of the alternatives. The final centerline and ROW will be identified after the route is<br />
selected through the environmental review and permitting process.<br />
Ancillary facilities necessary to support the project include new or upgraded substations and a breaker<br />
station. Each of the routes and ancillary facilities are described below.<br />
Route 1 generally follows the Great Lakes Gas Transmission Company (Great Lakes) pipeline right‐ofway<br />
from the Wilton Substation to just east of Deer River, where it then follows a Minnesota Power<br />
115 kV transmission line to the Boswell Substation.<br />
Route 2 generally follows U.S. Highway 2 (US 2) and the pipeline rights‐of‐way of Enbridge Pipelines LLC<br />
(Enbridge) for its entire length between the Wilton Substation and Boswell Substation.<br />
Route 3 bypasses the LLR by taking a more northerly route between Bemidji and Grand Rapids. This<br />
route generally parallels existing transmission line rights‐of‐way between Bemidji, Blackduck, Deer River,<br />
and Grand Rapids. Route 3 passes though the CNF in Itasca and Beltrami counties.<br />
Route options 1A, 1B, 1C, and 2C represent bypass routes that connect sections of Routes 1 and 2, and<br />
are intended to allow opportunities for connections between portions of the primary routes in order to<br />
avoid sensitive environmental resources.<br />
Certain upgrading of the Wilton Substation near Bemidji and the Boswell Substation near Grand Rapids<br />
would be required, as well as upgrading an existing 115 kV substation or building a new 230 kV<br />
substation in the Cass Lake area. Depending on the route selected, a breaker station may also be<br />
constructed at Nary Junction. The upgrades and proposed new construction are discussed below.<br />
Wilton Substation – The Project would not require physical expansion of the existing Wilton 230 kV<br />
Substation. Two new 230 kV breakers and a line termination structure would be added as a result of the<br />
Project, along with modifications to the existing 230 kV buses and relay panels. The Project would also<br />
require completion of a new ring bus section, as well as five new 230 kV switches with foundations, steel<br />
structures, and control panels.<br />
Boswell Substation – The Project would require the expansion of the Boswell 230 kV Substation by<br />
approximately 1.3 acres. No land procurement is required, however, because the entire expansion of<br />
the substation would be on Minnesota Power‐owned property. In addition to modifications to the<br />
existing 230 kV buses and relay panels, a new 230 kV breaker and a half bay would be added to the<br />
substation. This would involve installing two new 230 kV circuit breakers and 230 kV dead‐end<br />
structures, a new 230 kV bus, five new 230 kV switches, and associated foundations, steel structures,<br />
and control panels.<br />
Cass Lake Area Substation – The Project would require the expansion of the existing Cass Lake<br />
115/69 kV Substation or construction of a new 230/115 kV substation, depending on which route is<br />
selected. Routes 2 and 2C would require upgrading of the existing Cass Lake Substation. This would be<br />
accomplished by extending the existing fence line approximately 320 feet west. No land procurement<br />
would be required because the expansion of the substation would be on existing Otter Tail<br />
Power‐owned property. The expansion would be for the 230 kV equipment, which includes a 230 kV<br />
July 2010 Description of the Proposed Action Page 2‐4