Appendix F Detailed Cover Type Tables - USDA Rural Development
Appendix F Detailed Cover Type Tables - USDA Rural Development
Appendix F Detailed Cover Type Tables - USDA Rural Development
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Bemidji – Grand Rapids<br />
Biological Assessment and Evaluation<br />
three‐breaker ring bus with line switches, a new 230/115 kV transformer (approximately 187 million<br />
volt‐amperes [MVA]), and associated 115 kV facilities to integrate this transformer into the existing<br />
equipment.<br />
Routes 1, 1A, 1B, and 1C would require construction of a new substation near the intersection of the<br />
route and the existing Nary Junction – Cass Lake 115 kV line. It would be designed and constructed with<br />
a 230 kV three‐breaker ring bus with 230 kV line switches. The facility would include a 230/115 kV<br />
transformer of approximately 187 MVA that steps down the voltage to a 115 kV three‐breaker ring bus.<br />
In addition, the new substation would require a control house, relay panels, foundations, steel<br />
structures, and switches. The substation yard would be approximately 500 feet by 500 feet of yard fence<br />
and require an access road.<br />
Nary Breaker Station – In addition to the substation improvement mentioned above, Route 1A includes<br />
a section where the proposed 230 kV line would be double‐circuited with an existing 115 kV<br />
transmission line between Bemidji and Cass Lake. Double‐circuit construction, operation, and<br />
maintenance can have impacts on the security and reliability of the transmission system that must<br />
always be taken into account. The Applicants believe the Project could be double‐circuited with the<br />
existing 115 kV transmission lines between Bemidji and Cass Lake without significantly affecting area<br />
reliability, provided a 115 kV breaker station is constructed at Nary Junction.<br />
This 115 kV breaker station would be located adjacent to the existing switch at Nary Junction on an<br />
approximately five‐acre site with a fenced and graded area of approximately 200 feet by 200 feet. The<br />
breaker station would consist of three 115 kV circuit breakers and associated switches, communications,<br />
relay and control equipment, three 115 kV line termination structures, and a control house. An<br />
improved access road and small parking lot would also be required to move equipment to the site.<br />
Building this 115 kV breaker station sectionalizes the 115 kV circuits serving Bemidji, Cass Lake, Akeley,<br />
and Badoura. This provides back‐up (redundant) transmission in the event of an outage of the proposed<br />
230/115 kV double‐circuit transmission lines.<br />
2.3.4 Transmission Line Design<br />
While final engineering and design have not been completed, transmission line construction would likely<br />
use two‐pole H‐frame structures for a majority of the route (Figure 3 – Structure Figures). These are the<br />
typical structures used for a 230 kV transmission line located on wooded, rugged topography. They are<br />
also suited for areas requiring longer spans to avoid or minimize the placement of structures in wetlands<br />
or waterways. Each H‐frame structure would range in height from 70 to 90 feet, and be placed 600 to<br />
1,000 feet apart.<br />
Where conditions warrant, single‐pole structures may be used. For this Project, single pole structures<br />
would typically be used in areas where the available right‐of‐way is limited, such as along roads in<br />
developed areas. The height of single‐pole structures ranges from 80 to 100 feet, with the span between<br />
structures from 400 to 800 feet.<br />
The typical right‐of‐way for a 230 kV transmission line is approximately 125 feet wide. Ultimately, the<br />
right‐of‐way width depends upon the recommended clearances between the conductor and other<br />
facilities adjacent to the route. The width of the right‐of‐way may be reduced in certain high‐density,<br />
developed areas with the use of single‐pole construction. The width of the right‐of way may also be<br />
reduced where the new transmission line follows an existing linear corridor, such as another utility line<br />
or roadway. On the other hand, a wider right‐of‐way may be required for longer spans of the<br />
transmission line or where special design requirements are dictated by topography. The Applicants<br />
would seek permanent easements providing the right to construct, operate, and maintain the<br />
transmission line along the full width and length of its right‐of‐way, as necessary.<br />
July 2010 Description of the Proposed Action Page 2‐5