FINAL REPORT - San Bernardino Superior Court
FINAL REPORT - San Bernardino Superior Court
FINAL REPORT - San Bernardino Superior Court
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Section 4: SCLA Hangar Development<br />
Ground Lease Amended in February 2006<br />
On February 14, 2006, SCLAA amended the ground lease agreement with CBS Aviation<br />
Development two weeks after the entering into the second loan agreement and only three days<br />
before funds were disbursed. The lease amendment primarily eliminated the developer’s<br />
responsibilities relating to the cargo complex (which was to be completed by December 31, 2006<br />
under the original lease). It does not appear that funding was reduced or reevaluated as a result of<br />
this amendment.<br />
Additional Ground Lease Approved with CBS Aviation in July 2006, but Withheld by City<br />
At its regularly scheduled meeting on July 18, 2006, the SCLAA Board approved two additional<br />
ground lease agreements and amendments with CBS Aviation Development, LLC. Although the<br />
original lease with CBS Aviation and all amendments were requested as part of this audit, copies<br />
of these additional agreements and amendments were not provided to us by City management.<br />
SCLAA Severed Agreement with CBS Aviation & Brought in New Contractor<br />
In June and July of 2006, approximately seven months after the hangar facilities were to be<br />
completed under the lease agreement, about 25 subcontractors of CBS Aviation Development<br />
alerted City officials that they had not been paid by the company for work done on the hangars.<br />
On August 11, 2006, the City, SCLAA, CBS Aviation Development, and KND Affiliates, LLC<br />
(an LLC established by Jeff Kinsell, the principal of Kinsell, Newcomb, & De Dios, the City’s<br />
bond underwriter) entered into a settlement agreement to remove CBS Aviation Development<br />
from the project as the developer and replace it with KND Affiliates, LLC.<br />
Settlement Agreement Implies KND would Buyout CBS and Finance Remainder of Project<br />
The August 2006 settlement agreement implies that KND Affiliates, LLC would commit $70<br />
million to buy out the CBS leaseholder rights, repay the City’s previous loans to CBS, and<br />
complete the project. According to the settlement agreement, KND Affiliates agreed to accept<br />
the partially completed project and immediately place $19.2 million into an escrow account with<br />
$12.7 million intended for unpaid CBS subcontractors and $6.5 million to buy out CBS’s<br />
interests in the project. The settlement agreement also states that KND would place an additional<br />
$31.9 million into an escrow account to repay previous project financing and $18.8 million to<br />
complete the project. Essentially, according to the settlement agreement, KND would accept all<br />
assets and liabilities of CBS Aviation, including obligations to subcontractors, unpaid loan<br />
amounts, and the costs to complete the four hangar facilities. In return, KND would have the<br />
right to lease the facilities to tenants or sell the leased facilities to one or more institutional<br />
investors. The amounts of KND Affiliates’ implied financial commitments are summarized in<br />
Table 4.1 below.<br />
4-4<br />
Harvey M. Rose Associates, LLC