Section 4: SCLA Hangar Development<br />
Table 4.4<br />
Estimated Total Costs of Hangar Development Project<br />
Source Use Amount<br />
2005 Schedule A SCLAA Bonds CBS Construction Costs $17,730,000<br />
2006 Schedule A SCLAA Bonds CBS Construction Costs 7,653,425<br />
2006 Schedule A SCLAA Bonds<br />
(Refinanced)<br />
CBS Construction Costs 4,704,076<br />
2005 & 2006 SCLAA Bonds Costs of Bond Issuances 4,600,000<br />
SCLAA Loans to KND Affiliates 2<br />
SCLAA Loans to KND Affiliates<br />
Buyout of CBS Aviation<br />
Development Interests<br />
Payments to CBS Aviation<br />
Subcontractors in August 2006<br />
6,400,000<br />
12,640,071<br />
CBS Aviation Development Costs Subtotal $53,727,572<br />
SCLAA Loans to KND Affiliates KND Construction Costs 38,925,758<br />
SCLAA Loans to KND Affiliates KND Contingency & Excess Funds 2,037,611<br />
SCLAA Loans to KND Affiliates KND General Project Expenses 380,802<br />
SCLAA Loans to KND Affiliates<br />
KND Costs (Interest Accrual and<br />
Not Allocated)<br />
7,865,555<br />
KND Affiliates Costs Subtotal $49,209,726<br />
Estimated Total Costs of Hangar Development Project $102,937,298<br />
Source: City documentation on Hangar Development Project<br />
Conclusions<br />
In September 2005 the City Council, in its role as the Southern California Logistics Airport<br />
Authority (SCLAA) Board of Directors, entered into a no-bid agreement with CBS Aviation<br />
Development, LLC for the construction of hangar facilities at Southern California Logistics<br />
Airport. The development agreement was based on a proposal put forward by the manager/owner<br />
of CBS Aviation Development, an individual with no prior relationship to the City and whose<br />
background and competency was not fully known. Further, there is no evidence that sufficient<br />
background research was conducted on CBS Aviation Development or its owner until two<br />
months after the SCLAA entered into a ground lease agreement with the contractor.<br />
2 It is unclear the sources of funding provided to KND Affiliates by SCLAA.<br />
4-11<br />
Harvey M. Rose Associates, LLC