IV. Program Allocations<br />

<strong>Budget</strong> Variances<br />

The 35.1 percent increase for this subactivity is primarily due to additional cooperative funding<br />

requests in fiscal year 2013-14 for Reclaimed Water ($2.9 million), Brackish Groundwater Development<br />

($2.7 million), and Aquifer Recharge/Storage and Recovery Construction ($1.8 million) projects<br />

Major <strong>Budget</strong> Items<br />

Reclaimed Water projects ($23.1 million) such as: the TECO - Polk Power Station Reclaimed Water<br />

Interconnects to Lakeland/Polk County/Mulberry ($5.7 million) and Manatee County Regional 10 MG<br />

Reclaimed Water Storage Tank SE-3 ($2.6 million); Brackish Groundwater Development projects<br />

($6.1 million) primarily for the Clearwater-5 MGD Brackish <strong>Florida</strong>n Aquifer Reverse Osmosis System<br />

($6 million); and the District expanded the benefits reuse of reclaimed water with cost effective storage<br />

alternative type projects in fiscal year 2013-14 by funding for Aquifer Recharge/Storage & Recovery<br />

Construction projects ($2.4 million) such as the Northwest Hillsborough Regional Aquifer Storage and<br />

Recovery Project ($1.5 million).<br />