<strong>Field</strong> Harris<strong>on</strong><br />

Area Southern North Sea<br />

Operator C<strong>on</strong>ocoPhillips<br />

<strong>Development</strong> c<strong>on</strong>cept Platform or subsea<br />

Transport c<strong>on</strong>cept 10km pipeline to Kelvin?<br />

Start-up 2012<br />

Comments: The target start-up date for Harris<strong>on</strong>, a small gas field, has been put back to<br />

2012, according to partner Tullow. The field is expected to de developed with a single well,<br />

either housed <strong>on</strong> a minimum facilities platform or completed subsea, and tied back to the<br />

Kelvin platform, which itself is c<strong>on</strong>nected to the Murdoch field centre. The small K4 field, which<br />

could be developed in the same way, does not appear to be under c<strong>on</strong>siderati<strong>on</strong> for<br />

development at present. Harris<strong>on</strong> is about 10 km from Kelvin and K4 five km. Timing will have<br />

to fit in with other Murdoch tiebacks such as Cygnus.<br />

<strong>Field</strong> Hood<br />

Area Central North Sea<br />

Operator Iranian Oil Company (IOC)<br />

<strong>Development</strong> c<strong>on</strong>cept Subsea or floater<br />

Transport c<strong>on</strong>cept --<br />

Start-up 2012/13<br />

Comments: IOC is pushing ahead with plans to develop the Hood field following a successful<br />

appraisal well in mid 2008. The drilling campaign included an explorati<strong>on</strong> well <strong>on</strong> a nearby<br />

Paleocene prospect. Both wells were suspended. Senergy is analysing the well results and<br />

development opti<strong>on</strong>s; the development c<strong>on</strong>cept is due to be decided within a few m<strong>on</strong>ths,<br />

according to IOC. The company, which is sole licensee, will then resolve the issue of a partner<br />

which it plans to take <strong>on</strong> to operate the development. <strong>Development</strong> opti<strong>on</strong>s for Hood, whose<br />

reserves prior to the appraisal were estimated at 21m bbl, include a floater and a subsea<br />

tieback of some 20 km to Piper.<br />

www.intsok.com<br />

| 19