<strong>Field</strong><br />
Kittiwake SAL System and Pipeline<br />
Area Central North Sea<br />
Operator Centrica<br />
<strong>Field</strong> facilities SAL system, weighs 200t, held in place by four built-in sucti<strong>on</strong><br />
buckets. The pipeline c<strong>on</strong>sists of two lengths of flexible flowline<br />
totalling 2.9 km.<br />
Producti<strong>on</strong> end --<br />
Comments: In 2009 Venture, now taken over by Centrica, received permissi<strong>on</strong> to remove the<br />
Kittiwake single anchor loading (SAL) system and pipeline. The equipment is <strong>on</strong> lease from<br />
Nordic Troll and Trym until Nov 2010, but the operator wished to start work last year with the<br />
retrieval of the flowline by Subsea 7 layship Seven Navica, which has duly taken place. The<br />
SAL system itself will be removed this year: it will be released from the seabed by pumping<br />
water into the sucti<strong>on</strong> buckets until they lift clear of the seabed, and then lifted to the surface by<br />
a crane-vessel.<br />
<strong>Field</strong><br />
Miller<br />
Area Central North Sea<br />
Operator BP<br />
<strong>Field</strong> facilities PDQ platform with 28,100t topsides supported by 17,500t, eightleg<br />
jacket. 22 wells drilled. Three pipelines: oil export 8km, 14in to<br />
Brae A, gas export 242km, 30in to St Fergus, gas import 9km,<br />
16in from Brae B.<br />
Producti<strong>on</strong> end Sept 2007<br />
Comments: In Feb BP submitted the first draft of its decommissi<strong>on</strong>ing progamme, in which it<br />
proposes to leave the jacket footings in place. The programme is expected to come out to<br />
public c<strong>on</strong>sultati<strong>on</strong> in about May. Comparative studies of decommissi<strong>on</strong>ing and disposal<br />
opti<strong>on</strong>s have been prepared and these have been reviewed by c<strong>on</strong>sultant Xodus. Well<br />
aband<strong>on</strong>ment was performed by the incumbent drilling c<strong>on</strong>tractor KCA Deutag between<br />
summer 2008 and May 2009; Schlumberger was c<strong>on</strong>tracted to provide cement services, Expro<br />
for plugs and perforating services and Norse Cutting & Aband<strong>on</strong>ment to cut all casing and<br />
c<strong>on</strong>ductors. The platform was installed in 1992 – the jacket was barge-launched and the<br />
topsides lifted <strong>on</strong> in eight major lifts, the largest being the 6,500t cellar deck. The field officially<br />
ceased producti<strong>on</strong> in Sept 2007.<br />