<strong>Field</strong> Barbara/Phyllis<br />
Area Central North Sea<br />
Operator Dana<br />
<strong>Development</strong> c<strong>on</strong>cept Subsea<br />
Transport c<strong>on</strong>cept 40km pipeline to Everest?<br />
Start-up Q4 2012<br />
Comments: A host has been selected and commercial terms agreed for the subsea tieback of<br />
the Barbara and Phyllis gas/c<strong>on</strong>densate fields, Dana reports. Producti<strong>on</strong> will be exported by a<br />
40km, 12in pipeline – which suggests the host will be BG’s Everest platform to the north. Startup<br />
has slipped a little further to late 2012. The next step will be a detailed FEED study, leading<br />
to project sancti<strong>on</strong> in Q4. While Phyllis is wholly owned by Shell and Exx<strong>on</strong>Mobil, Barbara lies<br />
<strong>on</strong> three different licences and a unitisati<strong>on</strong> agreement has been reached. Combined reserves<br />
are 230 bcf.<br />
<strong>Field</strong> Bentley<br />
Area Northern North Sea<br />
Operator Xcite<br />
<strong>Development</strong> c<strong>on</strong>cept Producti<strong>on</strong> facility + storage<br />
Transport c<strong>on</strong>cept Offshore loading<br />
Start-up EPS 2011/12<br />
Comments: Xcite is planning a phased development of the Bentley heavy-oil field in block<br />
9/3b. The next step is an appraisal well, 9/3b-R, to be drilled and tested this year – if<br />
successful, first oil could possibly come as early as 2011, the company says. By April it<br />
expects to sign a c<strong>on</strong>tract with ADTI for a jackup rig to drill the well. Challenger Minerals will<br />
farm into the field, taking a 4% stake and c<strong>on</strong>tributing $4m to the well costs. The financial<br />
burden will be eased to a degree by tax advantages offered in the 2009 budget. In Dec Fugro<br />
drilled a geotechnical test well which showed that a jackup can be used to drill the appraisal<br />
well, which at 110m water depth is at the limit for jackups. The same bore will be used for the<br />
appraisal well, which will also be drilled by Fugro. The c<strong>on</strong>tractor was the first member of the<br />
Bentley alliance, which Xcite envisages as a group of suppliers willing to take some risk in the<br />
development in return for appropriate reward. ADTI, which, like Challenger, is owned by<br />
Transocean, is also a member. Amec will help to plan the producti<strong>on</strong> test and provide<br />
development services. BP will provide services for the offtake and sale of the crude, and assist<br />
with securing $20m of financing for the development. Full field development will call for 50 plus<br />
wells and a fixed platform, but for the EPS an FPSO is <strong>on</strong>e of the opti<strong>on</strong>s. In all phases oil will<br />
be exported by shuttle tanker, so storage in some form will be required. Base-case reserves<br />
are estimated by RPS at 122m bbl.<br />
www.intsok.com<br />