Completed Construction and Reconstruction Works on Motorway Sections<br />

In <strong>2007</strong> the value of completed construction and reconstruction works on motorway sections (excluding<br />

agent compensation and liabilities from borrowings and bonds) amounted to EUR 609,510,986, which is<br />

2 percent above the plan.<br />

New motorway sections constructed in <strong>2007</strong> reached a total value of EUR 534,183,393, which is 7 percent<br />

above the plan.<br />

Scheduled and completed construction and reconstruction works on motorway sections in <strong>2007</strong><br />

(Amounts include financing costs for individual sections)<br />

Scheduled <strong>2007</strong> Completed <strong>2007</strong> Index<br />

Motorway section (EUR) (EUR) Completed <strong>2007</strong><br />

/ Scheduled <strong>2007</strong><br />

MARIBOR - LENART 35,433,064 35,796,384 101<br />

LENART - COGETINCI: Lenart - Spodnja Senarska 25,461,292 27,035,901 106<br />

HAJDINA - ORMOŽ: Hajdina - Ptuj 2,029,943 6,612,691 326<br />

BELTINCI - PINCE: BELTINCI — LENDAVA, Phase I 31,835,989 49,096,237 154<br />

LENART - BELTINCI: Cogetinci - VuËja vas 19,354,298 24,178,357 125<br />

Motorway PESNICA - SLIVNICA: Zrkovska cesta - Ptujska cesta 16,679,999 10,144,048 61<br />

PESNICA - SLIVNICA: Zrkovska — Pesnica link road 33,790,002 37,530,375 111<br />

BELTINCI - PINCE: LENDAVA — PINCE, Phase I 33,703,518 72,397,497 215<br />

Motorway PESNICA - SLIVNICA: Nova Zrkovska c., km 0.87 - km 3.8 1,220,001 4,059,334 333<br />

LENART - COGETINCI: SPODNJA SENARSKA — COGETINCI 39,827,205 42,139,313 106<br />

Motorway SLIVNICA — DRAŽENCI 26,444,109 25,473,939 96<br />

Draženci - Gruškovje, subsection of intern. border crossing<br />

Gruškovje — state border — additional program<br />

4,882,741 2,505,546 51<br />

PROJECT 1 — TOTAL 270,662,161 336,969,621 124<br />

RAZDRTO — VIPAVA: Rebernice 38,632,259 40,310,022 104<br />

Motorway KLANEC - ANKARAN: Connection to Port of Koper, Phase I 12,547,960 9,823,560 78<br />

Motorway KLANEC - ANKARAN: Petrol pump platform Bertoki 209,998 526 0<br />

Motorway KOPER — IZOLA 17,015,882 5,785,700 34<br />

PROJECT 4 — TOTAL 68,406,099 55,919,808 82<br />

ŠENTVID — KOSEZE 58,124,124 41,140,421 71<br />

BI» - HRASTJE: PONIKVE - HRASTJE 9,569,550 4,655,389 49<br />

ŠMARJE SAP - VIŠNJA GORA: Petrol pump platform Cikava 1,609,998 59,331 4<br />

PERAËICA - PODTABOR 11,161,683 11,442,034 103<br />

Motorway VRBA - PERAËICA 38,238,240 45,718,599 120<br />

Motorway HRASTJE - KRONOVO: Lešnica - Kronovo 27,639,455 31,067,551 112<br />

BI» - HRASTJE: PLUSKA - PONIKVE 13,452,799 7,210,640 54<br />

PROJECT 6 — TOTAL 159,795,849 141,293,964 88<br />

24 ANNUAL REPORT <strong>DARS</strong> d.d. <strong>2007</strong> BUSINESS REPORT