Part I - Ministry Of Education and Sports
Part I - Ministry Of Education and Sports
Part I - Ministry Of Education and Sports
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
equity, <strong>and</strong> gender parity.<br />
(vi) Facilitate children in Laroo School for War affected children<br />
The sector continued to provide operational support <strong>and</strong> disbursed funds to 624 war affected children<br />
<strong>and</strong> 4 traumatised children. The Belgianfunded government school which opened its doors in 2006<br />
serves child survivors of the 23year insurgency of the Lord Resistance Army (LRA). The school only<br />
caters for classes P.1 to P.6.<br />
(vii) Construction <strong>and</strong> rehabilitation of primary schools<br />
Under the Emergency Construction <strong>and</strong> Rehabilitation of Primary schools project, 38 schools were<br />
identified <strong>and</strong> 18 schools received funds for the construction, rehabilitation <strong>and</strong> provision of furniture.<br />
These schools among others include: Bujubi P.S in Mityana; Bugwe P.S <strong>and</strong> Namutumba C/U P.S in<br />
Namutumba; St. Thomas Catholic P.S in Bweyogerere; St. Aloysius Bukasa; Bbale Waswa P.S; <strong>and</strong><br />
Kasengejje P.S in Wakiso; Kagina P.S in Kabale; Kichekano P.S in Isingiro; Namukunyu P.S <strong>and</strong><br />
Nawanyago P.S in Kamuli; <strong>and</strong> St. Joseph Day <strong>and</strong> Boarding P.S Nazigo; Kirowozo C/U; <strong>and</strong><br />
Nakabalanga P.S in Mukono; Bundikahungu P.S in Bundibugyo; Kalububbu P.S in Sembabule; Patto<br />
P.S in Sironko; <strong>and</strong> Kigalagala P.S in Jinja;<br />
(viii) Under SFG/PRDP <strong>and</strong> Presidential Pledges Programmes<br />
A total budgetary provision of 71.4bn was earmarked for the implementation of various<br />
infrastructural developments in all Local Governments including all divisions. Tables 4.1.1 <strong>and</strong> 4.1.2<br />
show the progress of works for SFG Normal <strong>and</strong> SFG/PRDP during the period under review.<br />
Table: 4.1.Civil works under SFG Normal<br />
S/N Facilities Targets Finished % Not Non<br />
1 Classroom 133 17 13% 116 87%<br />
2 New Construction 571 427 75% 144 25%<br />
3 V.I.P Latrine Stances 2,028 1,114 55% 914 58%<br />
4 Furniture <strong>Of</strong>fice 119 0 0 119 100%<br />
5. Furniture Classrooms 8,305 3,696 45% 4,609 55%<br />
6. Teachers Houses 182 134 74% 48 26%<br />
Source: EMIS 2011<br />
Table: 4.2.Civil works under SFG/PRDP<br />
S/N Facilities Targets Finished &<br />
Ongoing<br />
% Performance Not<br />
Started<br />
Non<br />
Performance<br />
1 Classroom 237 104 44% 133 56%<br />
2 New Construction 638 463 73% 175 27%<br />
3 V.I.P Latrine Stances 1,235 604 49% 631 51%<br />
4 Furniture <strong>Of</strong>fice 139 82 59% 57 41%<br />
5. Furniture Classrooms 14,191 5,890 42% 8,301 58%<br />
6. Teachers Houses 382 190 50% 192 50%<br />