II. OBLIGATIONS OF THE CONTRACTOR<br />

A. DELIVERY<br />

1. Supplier shall deliver at his own expense <strong>the</strong><br />

awarded items at <strong>the</strong> a<strong>for</strong>ementioned NFA<br />

installations within thirty (30) calendar days upon<br />

receipt <strong>of</strong> <strong>the</strong> Notice to Proceed. Delivery shall be<br />

covered by a Charge Invoice <strong>and</strong> Delivery Receipt.<br />

2. Shall undertake <strong>the</strong> fitting/installation <strong>of</strong> <strong>the</strong><br />

following <strong>rice</strong> <strong>mill</strong> <strong>parts</strong>: abrasive rollers, screwed<br />

iron roller, pawl, iron roller, per<strong>for</strong>ated steel plates<br />

<strong>and</strong> per<strong>for</strong>ated steel screens, to ascertain<br />

con<strong>for</strong>mity to specifications.<br />

3. Shall personally or through his authorized<br />

representative, witness <strong>the</strong> inspection/physical<br />

verification to be conducted by <strong>the</strong> inspection team.<br />

4. Shall replace all rejected items within ten (10)<br />

calendar days from receipt <strong>of</strong> <strong>the</strong> Notice <strong>of</strong><br />

Rejection <strong>and</strong> that said rejected items shall remain<br />

with NFA to be withdrawn only upon delivery <strong>and</strong><br />

acceptance <strong>of</strong> <strong>the</strong> replacement.<br />

5. Failure to deliver <strong>and</strong> fit/install <strong>the</strong> materials on <strong>the</strong><br />

specified period <strong>for</strong> any cause not attributable to<br />

NFA shall make <strong>the</strong> supplier liable to liquidated<br />

damages as specified under Item III.<br />

6. All expenses, losses <strong>and</strong> damages which may be<br />

incurred while <strong>the</strong> items <strong>for</strong> delivery are in transit<br />

to <strong>the</strong> identified NFA installations shall be borne by<br />

<strong>the</strong> supplier.<br />

B. BILLING<br />

Supplier shall bill NFA upon completion <strong>of</strong> <strong>the</strong> delivery <strong>of</strong><br />

<strong>the</strong> <strong>bid</strong> quantity <strong>and</strong> shall be paid within fifteen (15)<br />

working days after <strong>the</strong> complete submission <strong>of</strong> <strong>the</strong><br />

required <strong>documents</strong>.<br />

III. LIABILITIES OF THE CONTRACTOR<br />

A. LIQUIDATED DAMAGES<br />

1. For failure to satisfactorily deliver <strong>the</strong> materials under<br />

<strong>the</strong> contract within <strong>the</strong> delivery period as stated,<br />

67