10.07.2015 Views

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Draft Supplemental Environmental Impact Statement<strong>Keystone</strong> <strong>XL</strong> <strong>Project</strong>In addition to <strong>the</strong> proposed <strong>pipeline</strong> crossings <strong>of</strong> waterbodies, <strong>the</strong>re would be temporaryequipment bridges installed across many waterways. The actual crossing method employedwould depend on any permit conditions from <strong>US</strong>ACE and o<strong>the</strong>r relevant regulatory agencies.Prior to <strong>the</strong> start <strong>of</strong> clearing along each <strong>pipeline</strong> construction spread, temporary bridges (e.g.,subsoil fill over culverts, timber mats supported by flumes, railcar flatbeds, or flexi-floatapparatus) would be installed across all perennial waterbodies to allow construction equipment tocross with reduced disturbance. Clearing crews would be allowed only one pass through <strong>the</strong>waterbodies prior to temporary bridge construction. All o<strong>the</strong>r construction equipment would berequired to use <strong>the</strong> bridges. Waterbodies would be crossed using one <strong>of</strong> four different open-cutmethods or <strong>the</strong> HDD method. These waterbody crossing methods are described below.<strong>2.1</strong>.9.1 Open-Cut Crossing MethodsFor most waterbodies to be crossed by <strong>the</strong> proposed <strong>Project</strong>, one <strong>of</strong> <strong>the</strong> open-cut methods listedbelow would be used:• Non-flowing open-cut crossing method (for waterbodies that do not have a perceptible flowat <strong>the</strong> time <strong>of</strong> construction);• Flowing open-cut crossing method;• Dry-flume open-cut method; or• Dry dam-and-pump open-cut method.The trenching, <strong>pipeline</strong> installation, and backfilling methods used for <strong>the</strong>se types <strong>of</strong> crossingswould be similar to <strong>the</strong> crossing methods described above.Non-Flowing Open-Cut Crossing MethodThe non-flowing open-cut method would be used for all waterbodies with no visible flow at <strong>the</strong>time <strong>of</strong> construction. In <strong>the</strong> event that intermittent waterbodies are dry or have non-moving waterat <strong>the</strong> time <strong>of</strong> crossing, <strong>Keystone</strong> would install <strong>the</strong> <strong>pipeline</strong> using this method. Detail 11 <strong>of</strong> <strong>the</strong>CMRP (Appendix G) is an illustration <strong>of</strong> a typical open-cut crossing method for non-flowingwaterbodies.Flowing Open-Cut Crossing MethodIf <strong>the</strong>re is flow at <strong>the</strong> time <strong>of</strong> construction, <strong>the</strong> flowing open-cut method would be used and <strong>the</strong>trench would be excavated through flowing water. If an intermittent waterbody is flowing whencrossed, <strong>Keystone</strong> would install <strong>the</strong> <strong>pipeline</strong> using this method. Backhoes operating from one orboth banks would excavate <strong>the</strong> trench within <strong>the</strong> streambed while water continues to flowthrough <strong>the</strong> construction work area (see Detail 12 <strong>of</strong> Appendix G, CMRP). In wider rivers, instreamoperation <strong>of</strong> equipment may be necessary. <strong>Keystone</strong> would trench through <strong>the</strong> channel,lower in a pipe that is weighted for negative buoyancy, <strong>the</strong>n backfill. The need for negativebuoyancy would be determined by detailed design and site-specific considerations at <strong>the</strong> time <strong>of</strong>construction. Material excavated from <strong>the</strong> trench generally would be placed at least 10 feet awayfrom <strong>the</strong> water’s edge unless stream width exceeds <strong>the</strong> reach <strong>of</strong> <strong>the</strong> excavation equipment.Sediment barriers would be installed where necessary to prevent excavated spoil from entering<strong>the</strong> water. Hard or s<strong>of</strong>t trench plugs would be placed to prevent <strong>the</strong> flow <strong>of</strong> water into <strong>the</strong> uplandportions <strong>of</strong> <strong>the</strong> trench. After installation, <strong>the</strong> grade would be restored to pre-construction<strong>Project</strong> Description <strong>2.1</strong>-56 March 2013

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!