10.07.2015 Views

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Draft Supplemental Environmental Impact Statement<strong>Keystone</strong> <strong>XL</strong> <strong>Project</strong>needed for line clearance would overlap <strong>the</strong> existing road or <strong>pipeline</strong> easement. The ROWwidths would be 50 feet when not along an existing corridor. Each power provider woulddevelop detailed power line construction procedures to address site specific conditions. Ingeneral, construction <strong>of</strong> <strong>the</strong> electrical distribution lines would involve <strong>the</strong> following:• ROW Acquisition/Easements: The electric power provider would obtain any necessaryeasements.• ROW Clearing: Limited clearing would be required along existing roads in native andimproved grasslands and croplands. Ei<strong>the</strong>r tree trimming or tree removal would be conductedto provide adequate clearance between <strong>the</strong> conductors and underlying vegetation.• Power Line Construction: Power line poles and associated structures would be delivered onflatbed trucks. Radial arm diggers would typically be used to excavate <strong>the</strong> required holes.Poles would be ei<strong>the</strong>r wood or steel and would be directly embedded into <strong>the</strong> excavated holesusing a mobile crane or picker truck where appropriate. Anchors may be required at anglesand dead ends.• Stringing: After <strong>the</strong> power line poles are in place, conductors (wires) would be strungbetween <strong>the</strong>m. Pulling or reeling areas would be needed for installation <strong>of</strong> <strong>the</strong> conductorwires which would be attached to <strong>the</strong> poles using porcelain or fiberglass insulators.• Restoration: After completion <strong>of</strong> distribution line construction, <strong>the</strong> disturbed areas would berestored. All litter and o<strong>the</strong>r remaining materials would be removed from <strong>the</strong> constructionareas and disposed <strong>of</strong> in accordance with regulatory requirements. Preconstruction contourswould be restored as closely as possible and reseeding would follow landownerrequirements.<strong>2.1</strong>.13 <strong>Proposed</strong> <strong>Project</strong> Decommissioning<strong>2.1</strong>.13.1 <strong>Proposed</strong> <strong>Project</strong> Life<strong>Keystone</strong> used a design life <strong>of</strong> 50 years to develop <strong>the</strong> engineering standards for <strong>the</strong> proposed<strong>Project</strong>. However, with implementation <strong>of</strong> <strong>the</strong> <strong>pipeline</strong> integrity management plan, <strong>the</strong> 57 SpecialConditions developed by PHMSA (see Appendix B, PHMSA 57 Special Conditions), and anoperations and maintenance program as described above, <strong>Keystone</strong> anticipates that <strong>the</strong> life <strong>of</strong> <strong>the</strong>proposed <strong>Project</strong> would be much longer. Many o<strong>the</strong>r <strong>pipeline</strong> companies have safely extended<strong>the</strong> duration <strong>of</strong> <strong>pipeline</strong> systems by replacing sections <strong>of</strong> pipe after finding anomalies and byreplacing or upgrading equipment and facilities at pump stations. As a result, it is not possible toidentify a specific number <strong>of</strong> years that <strong>the</strong> proposed <strong>Project</strong> may be in service.<strong>2.1</strong>.13.2 DecommissioningPHMSA has requirements that apply to <strong>the</strong> decommissioning <strong>of</strong> crude oil <strong>pipeline</strong>s in 49 CFRSection 195.402(c)(10) and in 49 CFR 195.59 and 195.402. These regulations require that forhazardous liquid <strong>pipeline</strong>s, <strong>the</strong> procedural manuals for operations, maintenance, and emergenciesmust include procedures for abandonment, including safe disconnection from an operating<strong>pipeline</strong> system, purging <strong>of</strong> combustibles, and sealing abandoned facilities left in place tominimize safety and environmental hazards (49 CFR 195.402). Fur<strong>the</strong>r, <strong>the</strong>se regulations requirethat for each abandoned onshore <strong>pipeline</strong> facility that crosses over, under, or through a<strong>Project</strong> Description <strong>2.1</strong>-86 March 2013

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!