10.07.2015 Views

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Draft Supplemental Environmental Impact Statement<strong>Keystone</strong> <strong>XL</strong> <strong>Project</strong><strong>Keystone</strong> anticipates a peak workforce <strong>of</strong> approximately 5,000 to 6,000 construction personnel.These personnel would consist <strong>of</strong> <strong>Keystone</strong> employees, contractor employees, constructioninspection staff, and environmental inspection staff. All workers would be trained and certifiedfor <strong>the</strong>ir specific field <strong>of</strong> work (e.g., welders would be qualified as required by 49 CFR 195.222and PHMSA Special Condition 18).<strong>Keystone</strong>, through its construction contractors and subcontractors, would attempt to hiretemporary construction staff from <strong>the</strong> local population. Assuming that qualified personnel areavailable, approximately 10 to 15 percent (50 to 100 people per spread) could be hired from <strong>the</strong>local workforce for each spread, although this may not be possible in rural areas. This may notbe possible in more rural areas and or areas with low unemployment.Cross-country <strong>pipeline</strong> construction would typically proceed at a pace <strong>of</strong> approximately20 constructed miles per calendar month per spread. Construction would occur in <strong>the</strong> followingapproximate sequence:• Two to three weeks (14 to 21 calendar days) <strong>of</strong> work on <strong>the</strong> ROW prior to <strong>the</strong> start <strong>of</strong>production welding. Activities would include clearing, grading, stringing, and ditching.• Production welding at an average rate <strong>of</strong> 1.25 miles <strong>of</strong> pipe welded per working day over a 6­day work week (over 7 calendar days), resulting in completion <strong>of</strong> an average <strong>of</strong> about7.5 miles <strong>of</strong> <strong>pipeline</strong> per week.• Seven weeks (49 calendar days) <strong>of</strong> additional work after completion <strong>of</strong> production welding.Activities would include nondestructive testing, field joint coating, pipe installation, tie-ins,backfill, ROW clean-up, hydrostatic testing, reseeding, and o<strong>the</strong>r ROW reclamation work.Those time periods and rates <strong>of</strong> progress were used as <strong>the</strong> basis for determining <strong>the</strong> duration <strong>of</strong>construction activities on <strong>the</strong> ROW presented in Table <strong>2.1</strong>-18 for various spread lengths.Construction in areas with greater congestion or higher population, in industrial areas, or in areasrequiring o<strong>the</strong>r special construction procedures could result in a slower rate <strong>of</strong> progress. Inaddition, approximately 1 month would be required for contractor mobilization before <strong>the</strong> workis started and 1 month would be required for contractor demobilization after <strong>the</strong> work is finished.<strong>2.1</strong>.10.2 Environmental Inspection<strong>Keystone</strong> would use environmental inspectors on each construction spread. The environmentalinspectors would review <strong>the</strong> proposed <strong>Project</strong> activities daily for compliance with state, federal,and local regulatory requirements and would have <strong>the</strong> authority to stop specific tasks as approvedby <strong>the</strong> chief inspector. The inspectors would also be able to order corrective action in <strong>the</strong> eventthat construction activities violate <strong>the</strong> provisions <strong>of</strong> <strong>the</strong> CMRP, landowner requirements, or anyapplicable permit requirements.<strong>2.1</strong>.11 Operations and MaintenanceThe proposed <strong>Project</strong> would be operated, maintained, monitored, and inspected in accordancewith 49 CFR 194 and 195 and o<strong>the</strong>r applicable federal and state regulations. <strong>Keystone</strong> has alsoagreed to incorporate 57 PHMSA <strong>Project</strong>-specific special conditions that address proposed<strong>Project</strong> operation, inspection, and monitoring (see Appendix B, PHMSA 57 Special Conditions).The operational requirements <strong>of</strong> 49 CFR 195 and <strong>the</strong> PHMSA <strong>Project</strong>-specific SpecialConditions related to operation <strong>of</strong> <strong>the</strong> proposed <strong>Project</strong> (Appendix B, PHMSA 57 Special<strong>Project</strong> Description <strong>2.1</strong>-64 March 2013

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!