10.07.2015 Views

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

2.1 Overview of the Proposed Project - Keystone XL pipeline - US ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Draft Supplemental Environmental Impact Statement<strong>Keystone</strong> <strong>XL</strong> <strong>Project</strong>and associated facilities would <strong>the</strong>n be erected. This would include installation <strong>of</strong> a block valveinto <strong>the</strong> mainline as well as two MLV block valves: one would be installed on <strong>the</strong> suction piping<strong>of</strong> <strong>the</strong> pumps and one would be installed on <strong>the</strong> discharge piping <strong>of</strong> <strong>the</strong> pumps as required by 49CFR 195.260.The crude oil piping, both aboveground and below ground, would be installed and pressuretestedusing methods similar to those used for <strong>the</strong> main <strong>pipeline</strong>. After successful testing, <strong>the</strong>piping would be tied into <strong>the</strong> main <strong>pipeline</strong>. Piping installed below grade would be coated forcorrosion protection as required by 49 CFR 195 Subpart H (Corrosion Control) and <strong>the</strong>applicable PHMSA special conditions. In addition, all below-grade facilities would be protectedby a CP system as required by Subpart H and <strong>the</strong> applicable PHMSA special conditions. Pumps,controls, and safety devices would be checked and tested to ensure proper system operation andactivation <strong>of</strong> safety mechanisms before being put into service. After hydrostatic testing <strong>of</strong> <strong>the</strong>below-grade equipment, <strong>the</strong> site would be graded and surfaced with gravel and a security fencewould be installed around <strong>the</strong> entire perimeter <strong>of</strong> each site. Construction activities and storage <strong>of</strong>construction materials would be confined to each pump station site. Figure <strong>2.1</strong>.4-1 (providedpreviously) shows a typical pump station with pigging facilities. Figure <strong>2.1</strong>.9-1shows a typicalpump station without pigging facilities.Mainline Valves and Delivery SitesMLV construction would occur during mainline <strong>pipeline</strong> construction. IMLV construction wouldbe carried out concurrently with <strong>the</strong> construction <strong>of</strong> <strong>the</strong> <strong>pipeline</strong>. Wherever practical, IMLVswould be located near public roads to allow year-round access. If necessary, permanent accessroads or approaches would be constructed to each fenced MLV site. The construction sequencewould consist <strong>of</strong> clearing and grading followed by trenching, valve installation, fencing, cleanup,and site restoration.<strong>2.1</strong>.10 Construction Schedule, Workforce, and Environmental Inspection<strong>2.1</strong>.10.1 Schedule and WorkforceConstruction <strong>of</strong> <strong>the</strong> proposed <strong>Project</strong> would begin if <strong>Keystone</strong> obtains all necessary permits,approvals, and authorizations. As currently planned, <strong>the</strong> proposed <strong>Project</strong> would be constructedusing 10 spreads <strong>of</strong> approximately 45 to 120 miles long (see Table <strong>2.1</strong>-18). Final spreadconfigurations and <strong>the</strong> final construction schedule may result in <strong>the</strong> use <strong>of</strong> additional spreads orfewer shorter or longer spreads. If <strong>Keystone</strong> obtains all permits, approvals, and authorizations itanticipates <strong>the</strong> proposed <strong>Project</strong> to be placed into service in 2015.Table <strong>2.1</strong>-18Representative Cross-Country Construction Times Based on Estimates <strong>of</strong>ScheduleSpread Length Pre-welding Welding TimePost-welding andClean-up Total Duration80 miles 21 days 75 days 49 days 145 days (21 weeks)90 miles 21 days 84 days 49 days 154 days (22 weeks)100 miles 21 days 94 days 49 days 164 days (24 weeks)120 miles 21 days 112 days 49 days 182 days (26 weeks)<strong>Project</strong> Description <strong>2.1</strong>-62 March 2013

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!