7. CONCLUSIONSIt is impossible to predict exactly what amount of which type of resources would beavailable to each facility at some price. However, under base case scenario #2, which assumesGRU, JEA, and TAL all use the biomass resources closest to them, the total amount of woodybiomass available for less than $3.00 per MMBtu delivered in the two-hour woodsheds of thethree facilities is 474,500 dry tons, or 7.20 TBtu, per year. Fifty-three percent of this total isurban wood waste within a two-hour haul of the three facilities, 37% is logging residues within a45-minute haul, and the remaining 10% is comprised of thinnings within a 30-minute haul. Thistotal includes 2.82 TBtu/year delivered to GRU, 2.56 TBtu/year to JEA, and 1.78 TBtu/yearTAL. The total consists of 11% of the wood waste, logging residues, and thinnings availablewithin a two-hour maximum haul of the three facilities.The least-cost biomass resources needed to provide 10.65 TBtu/year (enough to generatethree 40 MW facilities) in scenario #2 would be comprised of about 35% urban wood waste,42% logging residues, and about 20% from thinnings of natural stands and plantations. Toprovide 3.55 TBtu per year for each facility, the amount required to produce 40 MW, themarginal cost is expected to be $3.12, $3.23, and $3.25 per MMBtu at GRU, JEA, and TAL,respectively.About 3% of this least-cost supply of 10.65 TBtu/year would be met with nearby pulpwood(Figure 32). Pulpwood comprises 0%, 4%, and 6% of the least-cost resources used to provide 40MW for GRU, JEA, and TAL, respectively. The 10.65 TBtu/year needed to power these threefacilities, is 11% of the 100.91 TBtus/year from urban wood waste, logging residues, thinnings,and pulpwood identified within a two-hour haul of the three facilities. The resources included inthese scenarios are about 100%, 28%, 27%, 25%, 15%, and 0.4% of annually available urbanwood waste, logging resides, thinnings from longleaf pine restoration, thinnings fromoverstocked plantations, thinnings from overstocked natural stands, and pulpwood, respectively,within the two-hour one-way woodsheds, excluding overlap of adjacent woodsheds (Figure 33).115
OverstockedNatural Stands,0.16, 1% Pulpwood, 0.32,3%OverstockedPlantations,0.69, 6%LongleafRestoration,1.38, 13%Urban Wood,3.76, 35%LoggingResidues, 4.34,42%Figure 32. Total woody biomass resource composition to produce 10.65 TBtu/year for three(GRU, JEA, and TAL) 40 MW facilities under scenarios #2: “With competing demand” and #3:“With price competition”. Values shown are TBtu/year, followed by percent of the 10.65TBtu/year supply.116
- Page 3 and 4:
ACKNOWLEDGEMENTSThe authors acknowl
- Page 5 and 6:
4.2. Scenario A: Delivered to remot
- Page 7:
Figure 22. Projected softwood and h
- Page 10 and 11:
LIST OF ACRONYMS AND ABBREVIATIONSB
- Page 12 and 13:
1. INTRODUCTION1.1. Project Backgro
- Page 14 and 15:
Task-3: Transportation. Transportat
- Page 16 and 17:
2. TASK 1: WOODSHED DELINEATION AND
- Page 18 and 19:
calculations for urban wood waste a
- Page 20 and 21:
the current pulpwood harvests are a
- Page 22 and 23:
2,0001,800Acres (thousands)1,6001,4
- Page 24 and 25:
ton -1 ($17.38 green ton -1 ) for t
- Page 26 and 27:
$ per million BTU, delivered$4.00$3
- Page 28 and 29:
10.65 TBtu/year required to meet de
- Page 30 and 31:
haul time category in each county,
- Page 32 and 33:
Figure 9. TAL Hopkins two-hour one-
- Page 34 and 35:
Figure 11. GRU, JEA, and TAL woodsh
- Page 36 and 37:
Dry tonsrecoverableTBtu/yearRecover
- Page 38 and 39:
Dry tonsrecoverableTBtu/yearrecover
- Page 40 and 41:
Table 6. Results for scenario #3,
- Page 42 and 43:
Table 7. Results for scenario #4,
- Page 44 and 45:
Table 9. Results for scenario #6,
- Page 46 and 47:
6.005.004.00$/MMBtu3.002.001.001: W
- Page 48 and 49:
Resource/haul time categoryDry tons
- Page 50 and 51:
Resource/haul time categoryDry tons
- Page 52 and 53:
Table 12. Results for scenario #3,
- Page 54 and 55:
Table 13. Results for scenario #4,
- Page 56 and 57:
Table 15. Results for scenario #6,
- Page 58 and 59:
6.005.004.00$/MMBtu3.002.001.001: W
- Page 60 and 61:
Resource/haul time categoryDry tons
- Page 62 and 63:
Resource/haul time categoryDry tons
- Page 64 and 65:
Table 18. Results for scenario #3,
- Page 66:
Table 19. Results for scenario #4,
- Page 69 and 70: Resource/haul time categoryDry tons
- Page 71 and 72: 2.4.4. General resultsIt is difficu
- Page 73 and 74: Table 22. Yield, acreage required,
- Page 75 and 76: Table 25. Capital construction outp
- Page 77 and 78: 3. TASK 2: SUSTAINABILITY IMPACTS F
- Page 79 and 80: under this scenario are expected to
- Page 81 and 82: acres in 1995 to 8.5 MM acres in 20
- Page 83 and 84: 3.3. RESULTS3.3.1. GRUTable 27. Res
- Page 85 and 86: 5.004.504.003.50$/MMBtu3.002.502.00
- Page 87 and 88: Table 30. Results for the conservat
- Page 89 and 90: 3.3.3. TAL Hopkins facilityTable 31
- Page 91 and 92: 5.004.504.003.50$/MMBtu3.002.502.00
- Page 93 and 94: For GRU most of these do not apply;
- Page 95 and 96: Table 33. Concentration yard costs.
- Page 97 and 98: location of the rail siding and the
- Page 99 and 100: discussed, to get an idea of the pr
- Page 101 and 102: 5. TASK 4: CO 2 EMISSIONS FROM HARV
- Page 103 and 104: in fuel chips and the carbon in fue
- Page 105 and 106: transporting coal. However, because
- Page 107 and 108: 6. COMBINED RESOURCE AVAILABILITYPa
- Page 109 and 110: Resource/haul time categoryTBtu/yea
- Page 111 and 112: Table 39. Combined resources (resou
- Page 113 and 114: Resource/haul time categoryTBtu/yea
- Page 115 and 116: Resource/haul time categoryTBtu/yea
- Page 117: Resource/haul time categoryTBtu/yea
- Page 121 and 122: logging residues from 90% to 60% to
- Page 123 and 124: ecommend that GRU, in coordination
- Page 125: 9. REFERENCESBlack and Veach (2004)