Figure 1.4-1Project Development ScheduleDevelopment PhasePre-Sanction Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 – Yr 9 Yr 10 – Yr 14 Yr 15 – Yr 19Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4DPA PreparationRegulatory ApprovalsFront End EngineeringProponent's Approval(Sanction)Project PhaseStart-up and First OilOperations PhaseDevelopment Drillingand InstallationsProduction OperationsDecommissioning andAbandonmentWhite Rose DA Project Summary • January 2001 Page 26