DoDI 5000.02, January 7, 2015<br />

Table 2. Milestone and Phase Information Requirements, Continued<br />

INFORMATION REQUIREMENT<br />

FREQUENCY ALLOCATION APPLICATION<br />

(DD FORM 1494)<br />

MDAP<br />

PROGRAM TYPE 1 LIFE-CYCLE EVENT 1,2,3<br />

MAIS<br />

ACAT<br />

II<br />

≤ III<br />

MDD<br />

MS<br />

A<br />

CDD<br />

Val<br />

Dev<br />

RFP<br />

Rel<br />

MS<br />

B 5<br />

● ● ● ● ● ● ●<br />

MS<br />

C<br />

FRP/FD<br />

Dec<br />

OTHER<br />

SOURCE<br />

SEC. 104, P.L. 102-538 (Ref. (z))<br />

47 U.S.C. 305, 901-904 (Ref. (aa))<br />

APPROVAL<br />

AUTHORITY<br />

National<br />

Telecommunications<br />

and Information<br />

Administration<br />

STATUTORY for all systems/equipment that use the electromagnetic spectrum while operating in the United States and its possessions. The DD Form 1494, Application for Equipment Frequency Allocation, is<br />

available from http://www.dtic.mil/whs/directives/infomgt/forms/dd/ddforms1000-1499.htm. The STATUTORY requirement for milestone decisions is met when DD Form 1494 is submitted by the Program<br />

Manager to the appropriate reviewing and approving agencies. Generally not applicable to <strong>Defense</strong> Business System (DBS) programs.<br />

Full Funding Certification Memorandum ● ● ● ● ● ● Para. 2f <strong>of</strong> Enc. 10 <strong>of</strong> this instruction MDA/CAPE<br />

Regulatory. See paragraph 2f <strong>of</strong> Enclosure 10 to this instruction. Must be signed by the CAE and the Component Chief Financial Officer.<br />

INDEPENDENT COST ESTIMATE (ICE) ● ● ● ● ● ● ●<br />

10 U.S.C. 2434 (Ref. (g)(h))<br />

10 U.S.C. 2334 (Ref. (g)(h))<br />

DCAPE or<br />

DoD Component<br />

STATUTORY. Section 2 in Enclosure 10 provides detailed instructions for MDAPs and MAIS programs. The Milestone C requirement only applies when the milestone decision authorizes LRIP. The DCAPE will<br />

be the approval authority for ACAT ID and IAM programs; the Component will approve ACAT IC programs following review by DCAPE.<br />

INDEPENDENT LOGISTICS ASSESSMENT (ILA) ● ● ● ● <br />

SEC. 832, P.L. 112-81 (Ref. (v))<br />

Sec. 5 <strong>of</strong> Enc. 6 <strong>of</strong> this instruction<br />

STATUTORY for weapon system MDAPs only. For the FRP, the assessment, is required if the decision is more than 4 years after Milestone C. Assessments after FRP will be accomplished at a minimum<br />

interval <strong>of</strong> every 5 years after Initial Operational Capability (IOC).<br />

CAE<br />

Information Support Plan (ISP) ● ● ● ● ● <br />

DoDI 8330.01 (Ref. (ab))<br />

DoDI 8320.02 (Ref. (ac))<br />

DoDI 8410.03 (Ref. (ad))<br />

DoD Component or<br />

as delegated<br />

Regulatory. Applicable to all IT, including NSS. A draft 4 is due for Development RFP Release; approved at Milestone B. Unless waived, updated at the Critical Design Review. The ISP <strong>of</strong> record is due prior to<br />

Milestone C; an updated ISP <strong>of</strong> record may be required during O&S. Enter data on-line at https://gtg.csd.disa.mil/; requires an account and login with a Common Access Card.<br />

Table Notes:<br />

1. A dot (●) in a cell indicates the specific applicability <strong>of</strong> the requirement to program type and life-cycle<br />

event, and represents the initial submission requirement. Moving right across a row, a checkmark ()<br />

indicates the requirement for updated information.<br />

2. All <strong>of</strong> the “Life-Cycle Events” will not necessarily apply to all “Program Types.”<br />

3. Unless otherwise specified when discussed in this instruction, documentation for identified events will<br />

be submitted no later than 45 calendar days before the planned review.<br />

4. Requires a Program Manager-, PEO-, and CAE-approved draft.<br />

5. Information requirements that have been finalized and approved by the responsible authority in support <strong>of</strong> the Development<br />

RFP Release Decision Point do not have to be re-submitted prior to Milestone B unless changes have occurred. In that<br />

case, updated documents will be provided.<br />

6. Incrementally Deployed S<strong>of</strong>tware Intensive Programs (Model #3) do not have a Milestone C and consequently are not<br />

required to satisfy the Table 2 requirements associated with that milestone.<br />

Change 2, 02/02/2017 59<br />

ENCLOSURE 1