Refinery - II M&I SD Oct-Nov 2018
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
Nos. of exch./coolers. retubed<br />
There were considerable reduction in the anticipated list of replacement of piping jobs and the actual<br />
replacement was around 40% of the originally planned list.<br />
There was a huge reduction in the planned replacement of CT-7<br />
connected underground piping and finally executed after test<br />
pit inspection for about 30 metres against 250 metres<br />
scheduled originally.<br />
Huge volume of work in critical piping replacement especially<br />
in 1st piperack support location of Plants – 16, 17 & 18 (due to<br />
severe corrosion at bottom section) was taken up well in<br />
advance, pre-fabricated and executed for almost 90% of the<br />
planned scope.<br />
Partial replacement / internal de-choking of inlet headers of<br />
16-E-108 D1-D2 was required as anticipated, but the pipeline<br />
work was not taken up till the end of shutdown due to resource<br />
constraints and partial dechoking alone was attempted by<br />
window cutting at one or two locations.<br />
TEST PIT for CT-7 piping inspection<br />
The consolidated list of pipeline replacement, piping modification and thickness gauing executed unitwise –<br />
Planned vs Actual is shown as tabulated below:-<br />
INSPECTION EXECUTIVE SUMMARY<br />
Unit<br />
Retubing of Exchangers / Coolers (Planned VS Actual) – No. of tubes<br />
Planned<br />
Pre-Shutdown<br />
During shutdown<br />
Retubed Deferred Retubed Deferred Additional<br />
Retubed<br />
Actual Vs<br />
Planned<br />
14 3055 269 64 2482 240 133 2884 94 %<br />
15 11970 1490 2799 5270 2275 1412 8172 68 %<br />
Unit<br />
Confirm repl.<br />
Planned<br />
Thickness Gauging, Pipeline Replacement & Modification status:<br />
Actual<br />
Replacement<br />
Anticipate repl.<br />
Planned<br />
Actual<br />
Actual Vs<br />
Planned<br />
Cold Lines<br />
Planned<br />
Thickness Gauging<br />
Actual<br />
Hot Lines<br />
Planned<br />
Actual<br />
Actual<br />
Vs Planned<br />
Modification<br />
Planned<br />
Actual<br />
Actual<br />
Vs<br />
Planned<br />
16 12080 4720 276 5770 1200 0 10490 87 %<br />
17 36 0 0 0 36 26 26 72 %<br />
18 512 0 0 332 180 0 332 65 %<br />
19 0 0 0 0 0 0 0 0<br />
Total 27653 6479 3139 13854 3931 1571 21904 79 %<br />
1.6.1.4 PIPING, STRUCTURAL WORK & PSV’s:<br />
Meticulous planning done in Piping replacement work segregating list of pipelines in each plant for confirmed<br />
replacement, anticipated replacement, thickness gauging of hot & cold pipelines. Extensive replacement of<br />
piping was planned and execution of work was done to most of the extent but, there were shortage of<br />
contractor resources for execution in the end resulted in forced waiving of recommended replacements, NDT<br />
requirements, etc.,<br />
14 79 71 66 24 66 % 62 9 238 48 19 % 7 6 86 %<br />
15 58 45 10 4 72 % 69 66 267 80 43 % 40 32 80 %<br />
16 102 83 88 38 64 % 182 124 123 69 63 % 24 19 79 %<br />
17 40 20 28 12 47 % 67 67 13 13 100 % 4 3 75 %<br />
18 29 25 16 7 71% 53 53 21 18 96 % 16 11 69 %<br />
19 43 38 15 5 74 % 97 97 21 21 100 % 15 13 87 %<br />
Total 351 282 223 90 65 % 530 416 683 249 55 % 106 84 79 %<br />
In total, there was about 65% of the recommended replacement of piping jobs were completed.<br />
Thickness gauging of cold pipelines was completed for about 71% of pipelines before the start of shutdown<br />
and another 8% managed during the shutdown outage. In toto, 79% cold pipelines were only gauged<br />
becaused of delay in scaffolding provision<br />
36<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
37