15-D-601 Flushing Oil Tank<br />

Replacement of tank steam coils shall be planned.<br />

Replacement of top shell course & top cover shall be planned.<br />

015-H-03C VACUUM EJECTOR<br />

Nozzles shall be procured based on ejector performance.<br />

15-T-01A/B WASH OIL FILTER, 15-T-02A/B LVGO CR FILTER, 15-T-03A/B VACUUM DIESEL CR FILTER,<br />

15-T-204A/B HVGO CR FILTER, 15-T-205A/B MPA FILTER & 15-T-206 A/B<br />

ecommendations | Recommendations | Recommenda<br />

tions | Recommendations | Recommendations | Recommendatio<br />

| Recommendations | Recommendations | Recommendations | Rec<br />

dations | Recommendations | Recommendations | Recommendatio<br />

s | Recommendations | Recommendations | Recommendations | R<br />

endations | Recommendations | Recommendations | Recommenda<br />

694<br />

15-C-08 Naphtha Stabilizer<br />

Anticipate replacement of Tray No: 5<br />

Minor pittings in the shell & trays shall be monitored.<br />

15-C-09 Stabilizer Reflux Drum<br />

Internal painting shall be planned.<br />

15-C-10 Ammonia Solution Drum<br />

Anticipate drum leg support fireproofing repair.<br />

15-C-15 Vacuum Distillation Column<br />

Replacement of chimney trays CT-5 & CT-6 (as weld leaks were observed) shall be planned.<br />

Anticipate replacement of Demister pad.<br />

Anticipate replacement of all packing beds in consultation with PE.<br />

15-C-16 Hot Well Drum<br />

Anticipate internal painting as per the CPCL painting system XVI during next M&I.<br />

15-C-17 Tempered Water Drum<br />

Replace steam coil during next M&I.<br />

Anticipate shell external patch weld near stiffener location.<br />

Anticipate internal painting as per the CPCL painting system XI during next M&I.<br />

15-C-18 Decoking pot<br />

Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />

Technical - Inspection<br />

Anticipate patch welding/ weld repair in top cover plate.<br />

15-C-19 Chemical Addition pot<br />

Anticipate leg supports replacement<br />

15-C-41 Flare knock-out drum<br />

Carry out top platform safety handrails & monkey ladder as per the site condition.<br />

15-D-02 Caustic Solution Tank<br />

Replacement of entire tank shall be planned.<br />

Replacement of Anchor chair foundation bolts (4 nos).<br />

15-D-04 Corrosion Inhibitor Tank<br />

Anticipate patch plate welding on the shell in next M&I S/D.<br />

Replacement of Anchor chair foundation bolts (4 nos).<br />

These filters shall be taken for maintenance in the next available opportunity.<br />

8.1.3 EXCHANGERS:<br />

Recommendations | Recommendations | Recommendations | Re<br />

<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />

ions | Recommendations | Recommendations | Recommendati<br />

dations | Recommendations | Recommendations |<br />

tions | Recommendations | Recommend<br />

ndations | Recommendations<br />

ations | Recomm<br />

endati<br />

BPA FILTER<br />

Possibility of decongesting of the following 10 nos. exch. in this congested layout to be reviewed (PE & GE) &<br />

equipment wise dismantling/ erection plan of components during M&I to be made (Maint.)<br />

15-E-12 A / B CRUDE / DIESEL EXCHANGER<br />

15-E-14 CRUDE / HVGO EXCHANGER<br />

15-E-18 A / B STAB. FEED / BOTTOM EXCHANGER<br />

15-E-111 A / B CRUDE/MPA EXCHANGER<br />

15-E-113 CRUDE/ BPA EXCHANGER<br />

15-E-115 A / B CRUDE/ BPA EXCHANGER<br />

Test rings of around 30 nos. of exchangers/coolers to be procured/ made available.<br />

15-E-08 CRUDE / HVGO EXCHANGER<br />

Bull plugs seal welding shall be carried out.<br />

15-E-10 CRUDE / HVGO EXCHANGER<br />

Complete retubing with 8.0 mm transverse baffle in place of 6.0 mm in the next M&I.<br />

As test ring had difficulties in fixing due to dimension issues, the same shall be corrected or new one to be provided.<br />

15-E-16 A ATM.OVHD CONDENSER (FIN FAN COOLER)<br />

Anticipate Retubing during next M&I shutdown<br />

15-E-16 B ATM.OVHD CONDENSER (FIN FAN COOLER)<br />

Confirmed retubing during next M&I shutdown. Anticipate replacement of Inlet nozzles.<br />

15-E-16 C / D ATM.OVHD CONDENSER (FIN FAN COOLER)<br />

Anticipate retubing during next M&I shutdown<br />

15-E-16 E / F ATM.OVHD CONDENSER (FIN FAN COOLER)<br />

Confirmed retubing during next M&I shutdown<br />

Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />

Technical - Inspection<br />

<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />

695<br />

CONSOLIDATED SHUTDOWN<br />

RECOMMENDATIONS