Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />

Technical - Inspection<br />

Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />

Technical - Inspection<br />

metal surface to make it water wet & gets flushed by freeing the coke & releasing the volatile materials.<br />

Subsequently, steam rinsing is carried out & once the rinsing is completed, system will be cooled down keeping<br />

drain closed & vent to atmosphere. Final s<strong>amp</strong>ling will be done after ventilation of the equipment in order to<br />

conclude effectiveness of decontamination.<br />

Liquid phase decontamination:<br />

The system is filled up to pre-determined level & circulation is set up. Water s<strong>amp</strong>le is checked for HC free &<br />

steam is introduced into water to attain 60 Deg C to 70 Deg C. Then calculated quantity of chemical is injected at<br />

the predefined injection points along with steam & again steam is introduced to raise the temp. to 80 Deg C.<br />

Effluent formed is pumped out to predefined effluent tank for disposal (where oil & water phases will be separated<br />

out. Separated oil can be recycled to slop tank).<br />

Accepted limits after decontamination:<br />

Description Limit Description Limit<br />

Benzene level < 1% PPM LEL < 1%<br />

Odor No odor HC NIL<br />

H2S NIL Pyrophoric Iron NIL<br />

FCCU Main Column (16-C-01)– Shell bulge & FCC Debutanizer (16-C-59) CUI issue:<br />

Due to internal fire in FCCU Main Column especially at the structured packing zone (bed-no.2), inspection was<br />

insisting for removal of packing & providing access inside the fire affected zone and removal of external insulation<br />

along with scaffolding externally to assess & recommend repair procedures. However, access for both got delayed<br />

by the contractor, M/s. Shilpi Engg. due to resource constraints and the same was provided only on 22 nd day of<br />

shutdown (15 days after the fire incident). Multiple bulges were observed at the fire affected zone along with<br />

carburization of external layer of shell internal surface. It was recommended to replace the bulged section of shell<br />

for 6.25 m 2 area with insert plates, but externally patched up (for about 9.0 m 2 ) due to paucity of time.<br />

Event Chronology is as below:<br />

11.10.<strong>2018</strong> Internal pyropheric Fire incident reported<br />

16.10.<strong>2018</strong> All manways were opened & permit obtained<br />

17.10.<strong>2018</strong><br />

Inspection recommended for providing external scaffolding & insulation removal for<br />

detailed inspection at fire affected zone<br />

18.10.<strong>2018</strong> Bed packing removal started<br />

21.10.<strong>2018</strong> Bed packing removal completed & scaffolding started<br />

INSPECTION EXECUTIVE SUMMARY<br />

Decontamination Process in CDU-2 & FCCU:<br />

Vapor phase decontamination was adopted in majority of the loops (except the pre-heat trains) in CDU-<strong>II</strong> & FCCU.<br />

Decontamination of 6 loops [(1) pre-heat trains, (2) furnaces, (3) Atm. column, (4) Vacuum column, (5) stabilizer<br />

column & (6) product R/D loops)] & 10 loops was planned/commenced in CDU-<strong>II</strong> & FCCU respectively at 09:30 hrs<br />

09.10.18. Entire process was being planned to be done by chemical circulation & draining method only. However<br />

on 11.10.18, whitish smoke was noticed from FCCU main column (16-C-01) top section during blinding activities<br />

after completion of decontamination & subsequent check in DCS where temperature increase observed at the<br />

structured packing zone @ LCO section, it was suspected to be an internal fire due to the presence of pyrophoric<br />

iron. In view of this, suspecting ineffective decontamination due to vapour phase decontamination (only<br />

circulation method), it was decided immediately to fill up with liquid in FCCU Main column (oxidizer along with<br />

water & draining) and the liquid phase decontamination method was extended to CDU-2 Atmospheric / vacuum<br />

column also in order to ensure effectiveness of whole process. Due to this exercise of filling, soaking & draining in<br />

CDU columns, decontamination process time got extended by around 24 hours in Atmospheric Column & 57.5<br />

hours in Vacuum column. Further delays were noted for loop separation, decontamination equipment installation<br />

and water filling and the entire decontamination process was completed in 6 days. After opening of equipment,<br />

decontamination process was found ineffective in some of the circuits unlike the previous experience in Ref-3 M &<br />

I S/D in 2015 wherein most of the circuits including vacuum section were found almost clean and ready for box up<br />

stage.<br />

24.10.<strong>2018</strong> Bed 1/2/3/4 cleaning completed<br />

26.10.<strong>2018</strong> Bed-2 (fire zone) Scaffolding provided for inspection<br />

26.10.<strong>2018</strong> Shell bulging/distortion was noticed, Inspection activities done. IWL issued for insert plate<br />

01.11.<strong>2018</strong> Bed-2 external patch plating was decided & buffing started<br />

02.11.<strong>2018</strong> Extent of external patching was marked by inspection<br />

04.11.<strong>2018</strong> External patch plate Fit-up was cleared<br />

06.11.<strong>2018</strong> External patch plate welding completed & DPT cleared<br />

08.11.<strong>2018</strong> Bed-2 packing job done<br />

10.11.<strong>2018</strong> Manway boxed up<br />

Insulation removal job for the debutaniser was taken up in the fag end of the shutdown. Upon removal of<br />

insulation, severe scale was noticed at the insulation support ring area. Inspection was insisting for providing<br />

access externally for detailed inspection. However, scaffolding provision got delayed and the same was provided<br />

only on 28 th day of shutdown. Severe external corrosion & thinning out was noticed upon detailed inspection &<br />

recommended for patch plate provision at 4 ring locations. Welding of the external patches took almost for 8 days<br />

& the job was completed/boxup clearance given on 09.11.<strong>2018</strong>.<br />

48<br />

<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />

<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />